1159 S STEARNS DR 90035

Certificate Information: 1159 S STEARNS DR 90035

Application / Permit
22014-10000-02900
Plan Check / Job No.
B22LA11263
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan CONVERSION OF (E) DETACHED TWO CAR GARAGES INTO ONE ADU PER LAMC 12.22 A.33 (C)-(D)
Permit Issued
Issued on 3/8/2023
Issuing Office
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/29/2022 APPLICANT
Assigned to Plan Check Engineer 7/8/2022 DANIEL YIP
Corrections Issued 7/8/2022 DANIEL YIP
Applicant returned to address corrections 2/1/2023 HERNAN ARREOLA
Plan Check Approved 3/7/2023 DANIEL YIP
Issued 3/8/2023 APPLICANT
CofO in Progress 4/11/2024 STUART CHAPMAN
CofO Issued 6/14/2024 DEROLD HAUFF
Permit Finaled 6/14/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/12/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 9/12/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 9/14/2022 TREVOR QUAN
Sewer availability Cleared 9/14/2022 TREVOR QUAN
Construction within easement Cleared 11/10/2022 RIDWAN HARDY
HPOZ Cleared 3/2/2023 JONATHAN KAPLAN

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: NA37588       ,
Contractor Roofing Angels; Lic. No.: 1034782-B       ,
Contractor Serenity Builders & Developers Inc; Lic. No.: 1034782-B       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/5/2023 Partial Approval JOSE AVILA
Footing/Foundation/Slab 4/17/2023 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 4/21/2023 Partial Approval JOSE AVILA
METHANE-Barrier 4/21/2023 Approved JOSE AVILA
METHANE-Subgrade 4/21/2023 Approved JOSE AVILA
PLUMBING-Rough 6/21/2023 Corrections Issued JOSE AVILA
Rough-Elec/Plmb/HVAC 7/18/2023 Conditional Approval JOSE AVILA
Deputy Wood Construction 8/11/2023 Conditional Approval JOSE AVILA
Shower Pan 8/31/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 9/12/2023 Not Ready for Inspection JOSE AVILA
Interior/Exterior Lathing 9/15/2023 Approved JOSE AVILA
BUILDING-Rough-Frame 10/10/2023 Partial Approval JOSE AVILA
Insulation 10/12/2023 Approved JOSE AVILA
Interior/Exterior Lathing 11/7/2023 Approved JOSE AVILA
Underground Mechanical 1/2/2024 Partial Approval BRENDAN MORELLI
ELECTRICAL-Final 3/6/2024 Not Ready for Inspection STUART CHAPMAN
Final 3/6/2024 Corrections Issued STUART CHAPMAN
PLUMBING-Final 3/6/2024 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 3/19/2024 Approved STUART CHAPMAN
Drywall Nailing 3/19/2024 Approved STUART CHAPMAN
Final 3/19/2024 Corrections Issued STUART CHAPMAN
Footing/Foundation/Slab 3/19/2024 Approved STUART CHAPMAN
Green Building Final 3/19/2024 Approved STUART CHAPMAN
Green Building Rough 3/19/2024 Approved STUART CHAPMAN
METHANE-Final 3/19/2024 Approved STUART CHAPMAN
METHANE-Rough 3/19/2024 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 3/19/2024 SGSOV Approved STUART CHAPMAN
Smoke Detectors 3/19/2024 Approved STUART CHAPMAN
Final 3/20/2024 Corrections Issued STUART CHAPMAN
ELECTRICAL-Final 4/11/2024 Approved STUART CHAPMAN
Final 4/11/2024 OK to Issue CofO STUART CHAPMAN
HVAC-Final 4/11/2024 Approved STUART CHAPMAN
PLUMBING-Final 4/11/2024 Approved STUART CHAPMAN
Service/Power Release 4/11/2024 Approved STUART CHAPMAN
Pre-Inspection 5/9/2024 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 5/17/2024 Approved ARTHUR NEGRETE