6652 E HOUGH ST 90042
Certificate Information: 6652 E HOUGH ST 90042
- Application / Permit
- 22014-10000-02860
- Plan Check / Job No.
- B22LA11137
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL EX SFD WITH ADDITION OF 698 SF
- Permit Issued
- Issued on 9/28/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/4/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | JAD BASMA |
| Corrections Issued | 6/25/2022 | JAD BASMA |
| Building Plans Picked Up | 7/12/2022 | APPLICANT |
| Plan Check Approved | 9/20/2022 | JAD BASMA |
| Issued | 9/28/2022 | APPLICANT |
| Permit Finaled | 5/4/2026 | DEROLD HAUFF |
| CofO Issued | 5/4/2026 | DEROLD HAUFF |
| Permit Finaled | 5/4/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/20/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 8/16/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 8/17/2022 | CINDY QI |
| Hydrant and Access approval | Cleared | 9/13/2022 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 9/20/2022 | JAD BASMA |
Contact Information
| Contractor | Mdr Builders; Lic. No.: 741228-B | 342 S GERHART AVE LOS ANGELES, CA 90022 |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/23/2022 | Corrections Issued | AMY COLIN |
| Footing/Foundation/Slab | 12/8/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 12/8/2022 | Partial Approval | AMY COLIN |
| Sewer | 12/8/2022 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 12/15/2022 | Partial Approval | AMY COLIN |
| Green Building Rough | 12/15/2022 | Not Ready for Inspection | AMY COLIN |
| Insulation | 12/15/2022 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2023 | Partial Approval | AMY COLIN |
| BUILDING-Rough-Frame | 11/22/2023 | Not Ready for Inspection | ROY SPAULDING |
| ELECTRICAL-Rough | 11/22/2023 | Corrections Issued | ROY SPAULDING |
| Gas Test | 11/22/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 11/22/2023 | Approved | ROY SPAULDING |
| HVAC-Rough | 11/22/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 11/22/2023 | Approved | ROY SPAULDING |
| Shower Pan | 11/22/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 12/1/2023 | Approved | ROY SPAULDING |
| Insulation | 12/1/2023 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 12/1/2023 | Approved | ROY SPAULDING |
| Drywall Nailing | 12/8/2023 | Approved | ROY SPAULDING |
| Deputy Drilled-In Anchors | 9/30/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 2/7/2025 | Approved | CRAIG DAVIS |
| Final | 2/7/2025 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 2/7/2025 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 2/7/2025 | Approved | CRAIG DAVIS |
| Final | 3/2/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 3/2/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/2/2026 | SGSOV Not Ready | DAVID WILLIAMS |
| Final | 3/24/2026 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 3/24/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | DAVID WILLIAMS |
| Final | 4/30/2026 | OK to Issue CofO | DAVID WILLIAMS |