1585 W WALDRAN AVE 90041

Certificate Information: 1585 W WALDRAN AVE 90041

Application / Permit
22014-10000-02836
Plan Check / Job No.
B22LA11042
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
Convert (E) garage to ADU, and storage addition per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 6/27/2024
Issuing Office
Current Status
CofO Issued on 12/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2022 APPLICANT
Assigned to Plan Check Engineer 6/14/2022 SHANGQIN XIE
Corrections Issued 6/15/2022 SHANGQIN XIE
Plan Check Approved 9/14/2022 SHANGQIN XIE
Issued 6/27/2024 APPLICANT
CofO in Progress 12/10/2024 ROY SPAULDING
Permit Finaled 12/29/2024 DEROLD HAUFF
Permit Finaled 12/29/2024 DEROLD HAUFF
CofO Issued 12/29/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/24/2022 JEANIE LAM
Sewer availability Cleared 6/24/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/22/2022 JEANIE LAM
Low Impact Development Cleared 8/31/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 9/7/2022 CINDY QI
Grading Pre-Inspection Cleared 9/12/2022 LUKE GONZALES

Contact Information

Contractor D K R Construction Inc; Lic. No.: 1070450-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/13/2024 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 8/14/2024 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/14/2024 Approved CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 8/16/2024 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/10/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 9/10/2024 Approved ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 9/10/2024 Approved ROY SPAULDING
HVAC-Rough 9/10/2024 Approved ROY SPAULDING
PLUMBING-Rough 9/10/2024 Approved ROY SPAULDING
Shower Pan 9/17/2024 Approved ROY SPAULDING
Underground Mechanical 9/17/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 9/24/2024 Approved ROY SPAULDING
Insulation 9/27/2024 Approved ROY SPAULDING
Drywall Nailing 9/30/2024 Approved ROY SPAULDING
ELECTRICAL-Final 11/22/2024 Approved ROY SPAULDING
Final 11/22/2024 Conditional Approval ROY SPAULDING
Footing/Foundation/Slab 11/22/2024 Approved ROY SPAULDING
HVAC-Final 11/22/2024 Approved ROY SPAULDING
PLUMBING-Final 11/22/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 11/22/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 11/22/2024 Approved ROY SPAULDING
Final 12/10/2024 OK to Issue CofO ROY SPAULDING