1585 W WALDRAN AVE 90041
Certificate Information: 1585 W WALDRAN AVE 90041
- Application / Permit
- 22014-10000-02836
- Plan Check / Job No.
- B22LA11042
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- Convert (E) garage to ADU, and storage addition per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 6/27/2024
- Issuing Office
- Current Status
- CofO Issued on 12/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/14/2022 | SHANGQIN XIE |
| Corrections Issued | 6/15/2022 | SHANGQIN XIE |
| Plan Check Approved | 9/14/2022 | SHANGQIN XIE |
| Issued | 6/27/2024 | APPLICANT |
| CofO in Progress | 12/10/2024 | ROY SPAULDING |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
| Permit Finaled | 12/29/2024 | DEROLD HAUFF |
| CofO Issued | 12/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/24/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/24/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | JEANIE LAM |
| Low Impact Development | Cleared | 8/31/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 9/7/2022 | CINDY QI |
| Grading Pre-Inspection | Cleared | 9/12/2022 | LUKE GONZALES |
Contact Information
| Contractor | D K R Construction Inc; Lic. No.: 1070450-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/13/2024 | Conditional Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/14/2024 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/14/2024 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 8/16/2024 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/10/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 9/10/2024 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 9/10/2024 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 9/10/2024 | Approved | ROY SPAULDING |
| Shower Pan | 9/17/2024 | Approved | ROY SPAULDING |
| Underground Mechanical | 9/17/2024 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 9/24/2024 | Approved | ROY SPAULDING |
| Insulation | 9/27/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 9/30/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 11/22/2024 | Approved | ROY SPAULDING |
| Final | 11/22/2024 | Conditional Approval | ROY SPAULDING |
| Footing/Foundation/Slab | 11/22/2024 | Approved | ROY SPAULDING |
| HVAC-Final | 11/22/2024 | Approved | ROY SPAULDING |
| PLUMBING-Final | 11/22/2024 | Approved | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 11/22/2024 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 11/22/2024 | Approved | ROY SPAULDING |
| Final | 12/10/2024 | OK to Issue CofO | ROY SPAULDING |