15818 W HIGH KNOLL ROAD 91436

Certificate Information: 15818 W HIGH KNOLL ROAD 91436

Application / Permit
22014-10000-02822
Plan Check / Job No.
B22LA11004
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan 413 SF ADDITION TO SINGLE FAMILY STRUCTURE AND REFRAME PORTION OF ROOF.
Permit Issued
Issued on 2/16/2023
Issuing Office
Current Status
CofO Issued on 4/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2022 APPLICANT
Assigned to Plan Check Engineer 7/14/2022 MARCELA FRANQUEZ
Corrections Issued 7/20/2022 MARCELA FRANQUEZ
Quality Review Completed 7/29/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 11/8/2022 MARCELA FRANQUEZ
Plan Check Approved 12/20/2022 MARCELA FRANQUEZ
Issued 2/16/2023 APPLICANT
CofO in Progress 4/2/2025 JOHN COLEMAN
Permit Finaled 4/16/2025 JOHN JANSON
CofO Issued 4/16/2025 JOHN JANSON
Permit Finaled 4/16/2025 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/22/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/22/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/22/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/22/2022 ROMAN GUTIERREZ
BHO/Hillside ordinance Cleared 7/22/2022 ROMAN GUTIERREZ
Roof/Waste drainage to street Cleared 7/22/2022 ROMAN GUTIERREZ
Sewer availability Cleared 7/22/2022 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 7/25/2022 VASIL MIHALEV
Eng Process Fee Ord 176,300 Cleared 7/26/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 10/26/2022 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,
Engineer Shamsrad,, Shima; Lic. No.: C88470 12300 MONTECITO RD 47      SEAL BEACH, CA 90740

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/14/2024 No Access for Inspection VINCENT HANLEY
PLUMBING-Rough 3/27/2024 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 4/3/2024 Approved VINCENT HANLEY
Gas Test 7/1/2024 Partial Approval THOMAS FINNILA
PLUMBING-Rough 7/1/2024 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 7/9/2024 Approved THOMAS FINNILA
PLUMBING-Rough 7/10/2024 Partial Inspection THOMAS FINNILA
ELECTRICAL-Rough 7/18/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 8/20/2024 Approved HENRY KIM
Green Building Rough 8/20/2024 Approved HENRY KIM
Insulation 8/20/2024 Approved HENRY KIM
Verify Sprinkler Sign Off 8/20/2024 Approved HENRY KIM
Shower Pan 8/23/2024 Approved JEFFREY BULL
Drywall Nailing 8/28/2024 Approved SCOTT SOBEL
Interior/Exterior Lathing 8/29/2024 Approved SCOTT SOBEL
PLUMBING-Rough 1/14/2025 Partial Approval THOMAS FINNILA
Final 1/17/2025 Not Ready for Inspection THOMAS FINNILA
Green Building Final 1/17/2025 Not Ready for Inspection THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Not Ready THOMAS FINNILA
Smoke Detectors 1/17/2025 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 1/31/2025 Approved JOHN COLEMAN
Service/Power Release 2/13/2025 Not Ready for Inspection THOMAS FINNILA
Gas Test 2/14/2025 Approved THOMAS FINNILA
PLUMBING-Final 2/14/2025 Corrections Issued THOMAS FINNILA
Service/Power Release 2/18/2025 Approved THOMAS FINNILA
Gas Test 2/20/2025 Approved THOMAS FINNILA
PLUMBING-Final 2/20/2025 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 3/11/2025 SGSOV Approved KRISTEN CAUSEY
HVAC-Final 3/14/2025 Corrections Issued THOMAS FINNILA
Final 4/1/2025 OK to Issue CofO JOHN COLEMAN
Green Building Final 4/1/2025 Approved JOHN COLEMAN
Smoke Detectors 4/1/2025 Approved JOHN COLEMAN