823 E AMOROSO PL 90291
Certificate Information: 823 E AMOROSO PL 90291
- Application / Permit
- 22014-10000-02801
- Plan Check / Job No.
- B22LA10966
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT FIRST FLOOR AND SECOND FLOOR OF EXISTING SINGLE FAMILY DWELLING PER ENGINEERED DESIGN.
- Permit Issued
- Issued on 4/24/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/8/2022 | SAMUEL GONZALEZ |
| Corrections Issued | 6/9/2022 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 6/13/2022 | APPLICANT |
| Plan Check Approved | 3/23/2023 | GEORGE ALVAREZ |
| Issued | 4/24/2023 | APPLICANT |
| CofO in Progress | 3/15/2024 | HERBERT GIRON |
| Permit Finaled | 3/20/2024 | DANIEL ORRANTE |
| CofO Issued | 3/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 3/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/25/2022 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2022 | SAUL GARCIA |
| Coastal Zone | Cleared | 2/8/2023 | MAXFIELD VERMY |
| Specific Plan | Cleared | 3/23/2023 | SPENCER WEJROWSKI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/23/2023 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 6/26/2023 | Approved | EVAN COOPER |
| Wood Frame | 7/17/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 10/17/2023 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 10/19/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 10/19/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 10/24/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/20/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 11/20/2023 | Approved | HERBERT GIRON |
| Insulation | 11/20/2023 | Approved | HERBERT GIRON |
| Shower Pan | 11/20/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 11/28/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 11/28/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 3/14/2024 | Approved | HERBERT GIRON |
| Final | 3/14/2024 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 3/14/2024 | Approved | HERBERT GIRON |
| HVAC-Final | 3/14/2024 | Approved | HERBERT GIRON |
| PLUMBING-Final | 3/14/2024 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 3/14/2024 | Approved | HERBERT GIRON |