9500-9502 N HATILLO AVE 91311

Certificate Information: 9500-9502 N HATILLO AVE 91311

Application / Permit
22014-10000-02795
Plan Check / Job No.
B22LA10946
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST SFD ADDITION AND 2ND STORY ADU ADDITION TO EXISTING SFD W GARAGE PER 12.22 A33 C & E
Permit Issued
Issued on 2/24/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2022 APPLICANT
Assigned to Plan Check Engineer 6/24/2022 STARR CHEN
Corrections Issued 7/19/2022 STARR CHEN
Quality Review Completed 7/20/2022 KEN GILL
Building Plans Picked Up 7/25/2022 APPLICANT
Applicant returned to address corrections 9/28/2022 STARR CHEN
Applicant returned to address corrections 10/19/2022 STARR CHEN
Plan Check Approved 2/15/2023 DANIEL YIP
Issued 2/24/2023 APPLICANT
CofO in Progress 11/13/2024 DAVID SCANTLIN
Permit Finaled 12/6/2024 JOHN JANSON
CofO Issued 12/6/2024 JOHN JANSON
Permit Finaled 12/6/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/1/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 11/1/2022 ROMAN GUTIERREZ
Sewer availability Cleared 11/1/2022 ROMAN GUTIERREZ
Hydrant and Access approval Cleared 1/9/2023 LAVEON RIDER
Low Impact Development Cleared 2/6/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/6/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 2/6/2023 JOSE DUARTE-DIAZ
Public Works-Sewers Cleared 2/15/2023 ROMAN GUTIERREZ
Public Works-Open Permits Cleared 2/15/2023 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/17/2023 Approved JOHN KIDWELL
Deputy Reinf. Concrete 5/24/2023 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval JOHN KIDWELL
PLUMBING-Rough 6/14/2023 Partial Approval JOHN KIDWELL
Deputy Wood Construction 8/31/2023 Conditional Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 9/1/2023 Approved DAVID SCANTLIN
Green Building Rough 9/1/2023 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 10/24/2023 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 10/24/2023 Partial Approval DAVID SCANTLIN
Green Building Rough 10/24/2023 Approved DAVID SCANTLIN
Interior/Exterior Lathing 10/24/2023 Approved DAVID SCANTLIN
PLUMBING-Rough 10/24/2023 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/21/2023 Approved DAVID SCANTLIN
ELECTRICAL-Rough 11/21/2023 Approved DAVID SCANTLIN
HVAC-Rough 11/21/2023 Approved DAVID SCANTLIN
Insulation 11/28/2023 Approved JEFFREY HARTLINE
Drywall Nailing 12/15/2023 Approved DAVID SCANTLIN
Final 8/26/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 8/26/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 8/26/2024 Approved DAVID SCANTLIN
Final 11/12/2024 OK to Issue CofO DAVID SCANTLIN
Green Building Final 11/12/2024 Approved DAVID SCANTLIN
Service/Power Release 11/13/2024 Approved DAVID SCANTLIN