2076 N WOLLAM ST 90065
Certificate Information: 2076 N WOLLAM ST 90065
- Application / Permit
- 22014-10000-02793
- Plan Check / Job No.
- B22LA10942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY ADDITION TO EXISTING 1 STORY SFD "COMPLY WITH DEPARTMENT ORDER effective date 11/29/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" CEIS Case Number is 995070.
- Permit Issued
- Issued on 3/27/2024
- Issuing Office
- Metro
- Current Status
- Issued on 3/27/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | STARR CHEN |
| Corrections Issued | 7/20/2022 | STARR CHEN |
| Quality Review Completed | 7/29/2022 | KEN GILL |
| Building Plans Picked Up | 8/2/2022 | APPLICANT |
| Applicant returned to address corrections | 3/1/2024 | STARR CHEN |
| Applicant returned to address corrections | 3/20/2024 | STARR CHEN |
| Plan Check Approved | 3/27/2024 | STARR CHEN |
| Issued | 3/27/2024 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/11/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2022 | WALLIE JONG |
| Sewer availability | Cleared | 8/22/2022 | WALLIE JONG |
| Tenant Habitability Plan | Cleared | 8/25/2022 | MICHAEL SOTO |
| Grading Pre-Inspection | Cleared | 8/24/2023 | ROBERT HUGHES |
| Specific Plan | Cleared | 1/3/2024 | RYAN LY |
| GPI Written Notices | Cleared | 3/1/2024 | STARR CHEN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baich,, Brendon Chad; Lic. No.: C83347 | PO BOX 8840 POMONA, CA 91701 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/15/2024 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/15/2024 | Not Ready for Inspection | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/16/2024 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 7/24/2024 | Approved | SCOTT FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Partial Approval | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Corrections Issued | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 11/21/2024 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/10/2025 | Approved | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/10/2025 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 2/10/2025 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/10/2025 | Not Ready for Inspection | THOMAS LOGRASSO |
| HVAC-Rough | 3/12/2025 | Approved | BRENDAN MORELLI |
| PLUMBING-Rough | 3/12/2025 | Corrections Issued | BRENDAN MORELLI |
| Special/Order Compliance | 3/12/2025 | Partial Inspection | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/14/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 3/14/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 3/14/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 3/25/2025 | Approved | REGINA MENDEZ |
| Drywall Nailing | 4/1/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 4/1/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 4/1/2025 | Approved | REGINA MENDEZ |
| Special/Order Compliance | 5/28/2025 | Partial Inspection | NICHOLAS LOPEZ |