10339 S HICKORY ST 90002

Certificate Information: 10339 S HICKORY ST 90002

Application / Permit
22014-10000-02737
Plan Check / Job No.
B22LA10724
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND ADDITION TO (N) DETACHED ADU
Permit Issued
Issued on 11/4/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2022 APPLICANT
Assigned to Plan Check Engineer 6/4/2022 KHUONG TRUONG
Corrections Issued 6/6/2022 KHUONG TRUONG
Building Plans Picked Up 6/9/2022 APPLICANT
Applicant returned to address corrections 9/13/2022 GEORGE ALVAREZ
Plan Check Approved 11/4/2022 FERNANDO FLORES
Issued 11/4/2022 APPLICANT
CofO in Progress 9/27/2023 JOHN KLARIN
CofO Issued 9/27/2023 ANSON MAGLASANG
Permit Finaled 9/27/2023 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/17/2022 JEANETTE VONG
Low Impact Development Cleared 10/13/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 10/28/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/2/2022 STEVE MELGAR
Sewer availability Cleared 11/2/2022 STEVE MELGAR
Hold Cleared 3/16/2023 MARIA VENDIVIL

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/17/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 3/22/2023 Approved JOHN KLARIN
PLUMBING-Rough 3/22/2023 Partial Approval JOHN KLARIN
BUILDING-Rough-Frame 4/18/2023 Not Ready for Inspection JAMES CHAVEZ
ELECTRICAL-Rough 4/18/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/18/2023 Approved JAMES CHAVEZ
Green Building Rough 4/18/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Rough 4/18/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 4/18/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Not Ready JAMES CHAVEZ
BUILDING-Rough-Frame 4/27/2023 Approved JAMES CHAVEZ
Green Building Rough 4/27/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 4/27/2023 Partial Inspection JAMES CHAVEZ
Underground Mechanical 4/27/2023 Approved JAMES CHAVEZ
Insulation 5/4/2023 Approved JOHN KLARIN
Drywall Nailing 5/10/2023 Approved JOHN KLARIN
Interior/Exterior Lathing 5/10/2023 Approved JOHN KLARIN
ELECTRICAL-Final 7/26/2023 Approved JOHN KLARIN
Final 7/26/2023 Corrections Issued JOHN KLARIN
HVAC-Final 7/26/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 7/26/2023 Approved JOHN KLARIN
ELECTRICAL-Final 8/3/2023 Approved JOHN KLARIN
Final 8/3/2023 Not Ready for Inspection JOHN KLARIN
Green Building Final 8/3/2023 Approved JOHN KLARIN
HVAC-Final 8/3/2023 Corrections Issued JOHN KLARIN
PLUMBING-Final 8/3/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 8/3/2023 Approved JOHN KLARIN
Final 9/20/2023 Corrections Issued JOHN KLARIN
Final 9/26/2023 OK to Issue CofO JOHN KLARIN
HVAC-Final 9/26/2023 Approved JOHN KLARIN