2003 S VICTORIA AVE 90016

Certificate Information: 2003 S VICTORIA AVE 90016

Application / Permit
22014-10000-02733
Plan Check / Job No.
B22LA10644
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
FIRST FLOOR ADDITION (22' X 22', 613.5 SQFT) TO THE REAR & NEW COVERED DECK ALSON A NEW ROOF DECK ON THE ROOF OF THE ADDITION.
Permit Issued
Issued on 1/22/2026
Issuing Office
Metro
Current Status
Issued on 1/22/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 NGHI SU
Corrections Issued 7/13/2022 NGHI SU
Quality Review Completed 7/22/2022 FARUK SEZER
Building Plans Picked Up 8/12/2022 APPLICANT
Plan Check Approved 4/2/2024 NGHI SU
Issued 1/22/2026 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/16/2023 STEVE MELGAR
Sewer availability Cleared 10/16/2023 STEVE MELGAR
Hydrant and Access approval Cleared 10/20/2023 MATTHEW CRAIG
Low Impact Development Cleared 3/22/2024 SAMUEL LINN
Roof/Waste drainage to street Cleared 3/26/2024 WALLIE JONG

Contact Information

Contractor Magco Contractors/Builders Inc; Lic. No.: 1116739-B 4106 EILEEN ST      RIVERSIDE, CA 92504
Engineer Gorgy,, Moheb Shohdy; Lic. No.: C53260 12370 FAIRBANKS DR.      TUSTIN, CA 92782

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/27/2026 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 1/29/2026 Approved JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 2/13/2026 Partial Approval JUSTIN HAWLEY
Underground Mechanical 2/13/2026 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 2/23/2026 Partial Approval JUSTIN HAWLEY
Insulation 2/23/2026 Partial Approval JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 3/11/2026 Partial Approval WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 3/19/2026 Partial Approval JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 3/19/2026 Corrections Issued JUSTIN HAWLEY
Green Building Rough 4/2/2026 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/2/2026 Partial Approval JUSTIN HAWLEY
BUILDING-Rough-Frame 4/6/2026 Approved WILLIAM SIERRA
Insulation 4/6/2026 Corrections Issued WILLIAM SIERRA
Rough-Elec/Plmb/HVAC 4/6/2026 Approved WILLIAM SIERRA
Shower Pan 4/6/2026 Approved WILLIAM SIERRA
Drywall Nailing 4/23/2026 Approved JUSTIN HAWLEY
Insulation 4/23/2026 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 4/23/2026 Approved JUSTIN HAWLEY