3948 S TIVOLI AVE 90066

Certificate Information: 3948 S TIVOLI AVE 90066

Application / Permit
22014-10000-02727
Plan Check / Job No.
B22LA10621
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION TO (E) SFD
Permit Issued
Issued on 11/17/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/2/2022 APPLICANT
Assigned to Plan Check Engineer 6/4/2022 FERNANDO FLORES
Corrections Issued 6/4/2022 FERNANDO FLORES
Building Plans Picked Up 6/9/2022 APPLICANT
Plan Check Approved 7/5/2022 GEORGE ALVAREZ
Issued 11/17/2022 APPLICANT
CofO in Progress 11/21/2023 JESUS RODRIGUEZ
Permit Finaled 12/5/2023 DANIEL ORRANTE
CofO Issued 12/5/2023 DANIEL ORRANTE
Permit Finaled 12/5/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/28/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 7/7/2022 CATHERINE ADROVER

Contact Information

Contractor F S Builders Group Inc; Lic. No.: 999313-B 19016 ARCHWOOD ST UNIT 9      RESEDA, CA 91335
Engineer Ng,, Edward Tw; Lic. No.: C38552 979 E MUNCIE AVE      FRESNO, CA 93720

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 1/13/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 1/13/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 1/13/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 1/13/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/1/2023 Partial Approval JESUS RODRIGUEZ
Green Building Rough 2/1/2023 Not Ready for Inspection JESUS RODRIGUEZ
Service/Power Release 2/1/2023 Approved JESUS RODRIGUEZ
Shower Pan 2/1/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 2/3/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/3/2023 Approved JESUS RODRIGUEZ
Shower Pan 2/3/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 2/17/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 3/8/2023 Approved EVAN COOPER
Green Building Rough 3/8/2023 Approved EVAN COOPER
Insulation 3/8/2023 Approved EVAN COOPER
Interior/Exterior Lathing 3/8/2023 Approved EVAN COOPER
Drywall Nailing 3/10/2023 Approved JESUS RODRIGUEZ
Special/Order Compliance 3/10/2023 Partial Inspection JESUS PINEDA
ELECTRICAL-Final 7/10/2023 Approved JESUS RODRIGUEZ
Final 7/10/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 7/10/2023 Approved JESUS RODRIGUEZ
HVAC-Final 7/10/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 7/10/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 7/10/2023 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 7/10/2023 Approved JESUS RODRIGUEZ
Final 11/21/2023 OK to Issue CofO JESUS RODRIGUEZ