367 N RIDGEWOOD PL 90004

Certificate Information: 367 N RIDGEWOOD PL 90004

Application / Permit
22014-10000-02720
Plan Check / Job No.
B22LA10583
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan convert exisitng detached garage (343sf) with addition to become ADU (800 SF max New Construction per State Law, CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g))
Permit Issued
Issued on 8/15/2022
Issuing Office
Current Status
CofO Issued on 1/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2022 APPLICANT
Assigned to Plan Check Engineer 6/13/2022 AUNG SOE
Plan Check Approved 8/9/2022 AUNG SOE
Issued 8/15/2022 APPLICANT
CofO in Progress 11/21/2024 JEFFREY MEAD
Permit Finaled 1/3/2025 DEROLD HAUFF
CofO Issued 1/3/2025 DEROLD HAUFF
Permit Finaled 1/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/23/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 6/23/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 8/5/2022 JEANIE LAM
Sewer availability Cleared 8/5/2022 JEANIE LAM

Contact Information

Contractor United 1 Construction; Lic. No.: 1002314-B       ,
Engineer Tran,, Duane; Lic. No.: C91229 1106 S NEWHOPE ST      SANTA ANA, CA 92704

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/18/2023 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 9/14/2023 Approved JEFFREY MEAD
Footing/Foundation/Slab 9/14/2023 Approved JEFFREY MEAD
Deputy Wood Construction 10/20/2023 Partial Approval SCOTT FINNILA
ELECTRICAL-Rough 10/20/2023 Partial Approval SCOTT FINNILA
PLUMBING-Rough 10/20/2023 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 10/20/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 10/24/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 10/25/2023 Approved SCOTT FINNILA
Rough-Elec/Plmb/HVAC 10/25/2023 Approved SCOTT FINNILA
Drywall Nailing 11/16/2023 Approved SCOTT FINNILA
Interior/Exterior Lathing 11/16/2023 Partial Approval SCOTT FINNILA
Final 4/25/2024 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 4/25/2024 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 4/25/2024 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Final 9/5/2024 Corrections Issued JEFFREY MEAD
Final 9/5/2024 Corrections Issued JEFFREY MEAD
HVAC-Final 9/5/2024 Approved JEFFREY MEAD
PLUMBING-Final 9/5/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 9/5/2024 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 9/5/2024 Approved JEFFREY MEAD
Final 9/13/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 9/13/2024 SGSOV Approved JOSE MACIAS
ELECTRICAL-Final 11/7/2024 Corrections Issued JOSE MACIAS
Final 11/7/2024 Corrections Issued JOSE MACIAS
ELECTRICAL-Final 11/20/2024 Approved JEFFREY MEAD
Final 11/20/2024 OK to Issue CofO JEFFREY MEAD
HVAC-Final 11/20/2024 Approved JEFFREY MEAD
PLUMBING-Final 11/20/2024 Approved JEFFREY MEAD