901 N VINE ST 90038

Certificate Information: 901 N VINE ST 90038

Application / Permit
22014-10000-02718
Plan Check / Job No.
B22LA10580
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
eplan CONVERT RECREATION ROOM/GYM @ 2ND FLOOR TO (3) ACCESSORY DWELLING UNIT IN (E) 5-STORY 70 UNIT APARTMENT BUILDING (1,819 SF) ADUs per GCS 65852.2(e)(i)(C)
Permit Issued
Issued on 4/3/2023
Issuing Office
Current Status
CofO Issued on 7/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2022 APPLICANT
Assigned to Plan Check Engineer 7/7/2022 ADRIANA LOPEZ
Corrections Issued 7/28/2022 ADRIANA LOPEZ
Quality Review Completed 7/28/2022 GARO TELMI
Plan Check Approved 2/21/2023 ADRIANA LOPEZ
Plan Check Approved 3/16/2023 ADRIANA LOPEZ
Issued 4/3/2023 APPLICANT
CofO in Progress 7/2/2024 TIMOTHY POWELL
Permit Finaled 7/9/2024 ERNESTO CORRAL
CofO Issued 7/9/2024 ERNESTO CORRAL
Permit Finaled 7/9/2024 ERNESTO CORRAL

Permit Application Clearance Information

ZI Cleared 8/2/2022 RYAN LY
Sewer availability Cleared 8/3/2022 ELAINE LEI
Fire Marshal Fire Life Safety Cleared 11/17/2022 SARAH ZHANG
Eng Process Fee Ord 176,300 Cleared 11/22/2022 THAN WIN
Green Code Cleared 1/18/2023 ADRIANA LOPEZ
DAS Clearance Cleared 1/19/2023 ADRIANA LOPEZ

Contact Information

Architect Benavidez,, Alexis; Lic. No.: C39253 15948 DEVONSHIRE ST      GRANADA HILLS, CA 91344
Contractor Hy-Max Building Corp; Lic. No.: 702339-B 425 W BROADWAY #410      GLENDALE, CA 91204
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 7/6/2023 Partial Inspection RONALD JIMENEZ
Drywall Nailing 8/1/2023 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 8/1/2023 Partial Approval RONALD JIMENEZ
Drywall Nailing 8/15/2023 Partial Approval RONALD JIMENEZ
Insulation 10/11/2023 Partial Approval RONALD JIMENEZ
Insulation 11/6/2023 Approved RONALD JIMENEZ
Light Gage Steel Frame 11/6/2023 Approved RONALD JIMENEZ
Drywall Nailing 11/14/2023 Partial Approval ALFREDO LOPEZ
Pre-Inspection 12/8/2023 Approved RONALD JIMENEZ
Drywall Nailing 1/17/2024 Partial Approval RICARDO ROBLES
Pre-Inspection 3/27/2024 Partial Inspection TIMOTHY POWELL
Final 7/2/2024 OK to Issue CofO TIMOTHY POWELL
Green Building Final 7/2/2024 Approved TIMOTHY POWELL
Green Building Rough 7/2/2024 Approved TIMOTHY POWELL
METHANE-Final 7/2/2024 Approved TIMOTHY POWELL
METHANE-Rough 7/2/2024 Approved TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Approved TIMOTHY POWELL
Smoke Detectors 7/2/2024 Approved TIMOTHY POWELL
Wood Frame 7/2/2024 Approved TIMOTHY POWELL