8314 S DELGANY AVE 90293

Certificate Information: 8314 S DELGANY AVE 90293

Application / Permit
22014-10000-02701
Plan Check / Job No.
B22LA10525
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE-STORY HOUSE REMODEL AND 1,137 SQ FT ADDITION TO THE FRONT & REAR
Permit Issued
Issued on 1/12/2023
Issuing Office
Metro
Current Status
CofO Corrected on 2/11/2025
Certificate of Occupancy
255789 - CofO Issued More Information
255789 - CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/16/2022 MARCELA FRANQUEZ
Corrections Issued 6/24/2022 MARCELA FRANQUEZ
Quality Review Completed 7/6/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/20/2022 MARCELA FRANQUEZ
Building Plans Picked Up 12/21/2022 APPLICANT
Plan Check Approved 1/12/2023 MARCELA FRANQUEZ
Issued 1/12/2023 APPLICANT
CofO in Progress 1/15/2025 TEMISTOCLES CAAL
CofO Issued-Status Void 2/3/2025 RICHARD STEINBACH
Permit Finaled-Status Void 2/3/2025 RICHARD STEINBACH
Re-Activate Permit 2/11/2025 RICHARD STEINBACH
Permit Finaled 2/11/2025 RICHARD STEINBACH
CofO Corrected 2/11/2025 RICHARD STEINBACH
Permit Finaled 2/11/2025 RICHARD STEINBACH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/6/2022 MARCELA FRANQUEZ
Sewer availability Cleared 7/22/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/27/2022 DINAH GARIN
Hydrant and Access approval Cleared 8/13/2022 RUEL COLE
Low Impact Development Cleared 12/9/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 1/9/2023 DINAH GARIN
GPI Written Notices Cleared 1/12/2023 MARCELA FRANQUEZ

Contact Information

Contractor Triad Pacific Inc; Lic. No.: 1020570-B 703 PIER AVENUE B399      HERMOSA BEACH, CA 90254
Engineer Kaligi,, Sean; Lic. No.: M37797 655 N CENTRAL AVE 17TH FL      GLENDALE, CA 91203
Engineer Kim,, Hong Kook; Lic. No.: C64529 3600 WILSHIRE BLVD STE 1903      LOS ANGELES, CA 90010
Engineer Tucker,, Keith D; Lic. No.: GE841 PO BOX 8133      HUNTINGTON BEACH, CA 92615

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/21/2023 Corrections Issued HERBERT GIRON
Excavation/Setback/Form/Re-Bar 2/22/2023 Off-Hour Fees Due
Footing/Foundation/Slab 2/22/2023 Partial Approval HERBERT GIRON
Special/Order Compliance 2/22/2023 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 3/9/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 3/9/2023 Partial Approval BOBBY KEY
Special/Order Compliance 3/9/2023 Corrections Issued BOBBY KEY
Wood Frame 3/9/2023 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 3/15/2023 Partial Approval JESUS RODRIGUEZ
Special/Order Compliance 3/15/2023 Partial Inspection JESUS PINEDA
Footing/Foundation/Slab 5/31/2023 Corrections Issued EVAN COOPER
METHANE-Barrier 5/31/2023 Approved EVAN COOPER
METHANE-Subgrade 5/31/2023 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 6/14/2023 Partial Approval BOBBY KEY
Gas Test 6/23/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 6/23/2023 Partial Approval BOBBY KEY
HVAC-Final 6/27/2023 Corrections Issued BOBBY KEY
HVAC-Rough 6/27/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 7/3/2023 Corrections Issued BOBBY KEY
HVAC-Rough 7/3/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 7/3/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 7/27/2023 Corrections Issued BOBBY KEY
Green Building Rough 7/27/2023 Not Ready for Inspection BOBBY KEY
METHANE-Rough 7/27/2023 Approved BOBBY KEY
Verify Sprinkler Sign Off 7/27/2023 Not Ready for Inspection BOBBY KEY
Deputy Wood Construction 7/28/2023 Conditional Approval BOBBY KEY
BUILDING-Rough-Frame 9/14/2023 Approved BOBBY KEY
Green Building Rough 9/14/2023 Approved BOBBY KEY
Interior/Exterior Lathing 9/14/2023 Partial Approval BOBBY KEY
Verify Sprinkler Sign Off 9/14/2023 Approved BOBBY KEY
Insulation 9/19/2023 Partial Approval BOBBY KEY
Drywall Nailing 10/11/2023 Approved BOBBY KEY
PLUMBING-Rough 10/26/2023 Partial Inspection KENNETH NAGLE
Interior/Exterior Lathing 11/15/2023 Approved TEMISTOCLES CAAL
Shower Pan 11/15/2023 Approved TEMISTOCLES CAAL
HVAC-Rough 2/23/2024 Approved BOBBY KEY
Pre-Inspection 7/12/2024 Partial Inspection BOBBY KEY
HVAC-Final 7/16/2024 Corrections Issued RICHARD STEINBACH
PLUMBING-Final 7/17/2024 Corrections Issued HERBERT GIRON
HVAC-Final 8/9/2024 Approved TEMISTOCLES CAAL
PLUMBING-Final 8/9/2024 Approved TEMISTOCLES CAAL
Special/Order Compliance 8/9/2024 Partial Inspection HERBERT GIRON
ELECTRICAL-Final 8/15/2024 Corrections Issued BOBBY KEY
ELECTRICAL-Final 8/21/2024 Approved BOBBY KEY
Final 10/25/2024 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 10/25/2024 Approved BOBBY KEY
Green Building Final 10/25/2024 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/25/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 10/25/2024 Approved BOBBY KEY
Final 1/14/2025 OK to Issue CofO TEMISTOCLES CAAL