403 W MANCHESTER AVE - 90003
Certificate Information: 403 W MANCHESTER AVE - 90003
- Application / Permit
- 22014-10000-02689
- Plan Check / Job No.
- B22LA10482
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan Remodel and Addition to Existing Single Family Dwelling
- Permit Issued
- Issued on 1/9/2023
- Issuing Office
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/1/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | MARCELA FRANQUEZ |
| Corrections Issued | 7/14/2022 | MARCELA FRANQUEZ |
| Quality Review Completed | 7/21/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/2/2022 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 1/3/2023 | MARCELA FRANQUEZ |
| Plan Check Approved | 1/5/2023 | MARCELA FRANQUEZ |
| Issued | 1/9/2023 | APPLICANT |
| CofO in Progress | 11/7/2024 | BOBBY KEY |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
| CofO Issued | 11/12/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/12/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2022 | DINAH GARIN |
| Sewer availability | Cleared | 8/2/2022 | DINAH GARIN |
| Specific Plan | Cleared | 8/3/2022 | VALERIA CEJA |
| GPI Written Notices | Cleared | 11/29/2022 | MARCELA FRANQUEZ |
| Grading Pre-Inspection | Cleared | 11/29/2022 | MARCELA FRANQUEZ |
| Low Impact Development | Cleared | 12/6/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/6/2022 | ANTHONY MAINEZ |
| Coastal Zone | Cleared | 12/8/2022 | DANIEL CORONADO |
Contact Information
| Architect | Hamilton,, John Patrick; Lic. No.: C28865 | 12240 VENICE BLVD SUITE 25 LOS ANGELES, CA 90066 |
| Architect | Hamilton,, John Patrick; Lic. No.: NA28865 | , |
| Contractor | Lemette Construction Design; Lic. No.: 1044314-B | 107 N REINO RD #206 NEWBURY PARK, CA 91320 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
| Engineer | Tuchscher,, James Todd; Lic. No.: NA77649 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/7/2023 | Conditional Approval | BOBBY KEY |
| Footing/Foundation/Slab | 4/5/2023 | Partial Approval | BOBBY KEY |
| METHANE-Barrier | 4/5/2023 | Not Ready for Inspection | BOBBY KEY |
| METHANE-Subgrade | 4/5/2023 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 4/19/2023 | Partial Approval | BOBBY KEY |
| Deputy Reinf. Concrete | 4/21/2023 | Conditional Approval | BOBBY KEY |
| Deputy Drilled-In Anchors | 5/10/2023 | Conditional Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Partial Approval | BOBBY KEY |
| METHANE-Rough | 5/15/2023 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 6/7/2023 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 7/11/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | BOBBY KEY |
| Deputy Steel/Welding | 10/25/2023 | Conditional Approval | JESUS PINEDA |
| BUILDING-Rough-Frame | 11/13/2023 | Corrections Issued | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 11/13/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 11/28/2023 | Partial Approval | BOBBY KEY |
| Interior/Exterior Lathing | 1/4/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 2/2/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 2/2/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 2/2/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 2/22/2024 | Approved | BOBBY KEY |
| Green Building Rough | 2/22/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 2/22/2024 | Approved | BOBBY KEY |
| METHANE-Rough | 2/22/2024 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 2/22/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/29/2024 | Approved | BOBBY KEY |
| Insulation | 2/29/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 3/11/2024 | Approved | BOBBY KEY |
| Shower Pan | 3/21/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 3/28/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/16/2024 | Corrections Issued | BOBBY KEY |
| Final | 8/16/2024 | Corrections Issued | BOBBY KEY |
| Green Building Final | 8/16/2024 | Approved | BOBBY KEY |
| HVAC-Final | 8/16/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 8/16/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 8/16/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/22/2024 | Approved | BOBBY KEY |
| Final | 8/22/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 8/22/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/22/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 8/22/2024 | SGSOV Approved | BOBBY KEY |
| Final | 11/7/2024 | OK to Issue CofO | BOBBY KEY |
| Service/Power Release | 11/7/2024 | Approved | BOBBY KEY |