7833 S NAYLOR AVE 90045
Certificate Information: 7833 S NAYLOR AVE 90045
- Application / Permit
- 22014-10000-02675
- Plan Check / Job No.
- B22LA10431
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AND INTERIOR REMODEL TO EXISTING ONE STORY SINGLE FAMILY DWELLING. ENCLOSE PORTION OF FRONT PORCH.
- Permit Issued
- Issued on 10/6/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | ZAW HAN |
| Corrections Issued | 6/9/2022 | ZAW HAN |
| Building Plans Picked Up | 6/10/2022 | APPLICANT |
| Applicant returned to address corrections | 8/8/2022 | FERNANDO FLORES |
| Plan Check Approved | 9/30/2022 | RICARDO RAMIREZ |
| Issued | 10/6/2022 | APPLICANT |
| CofO in Progress | 2/4/2025 | TEMISTOCLES CAAL |
| CofO Issued | 2/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | JENSON LEE |
| Sewer availability | Cleared | 7/12/2022 | JENSON LEE |
| Specific Plan | Cleared | 7/13/2022 | VALERIA CEJA |
| Grading Pre-Inspection | Cleared | 7/26/2022 | ROBERT HUGHES |
| Roof/Waste drainage to street | Cleared | 7/27/2022 | JENSON LEE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2024 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 4/30/2024 | Partial Inspection | HERBERT GIRON |
| Special/Order Compliance | 4/30/2024 | Partial Inspection | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 5/28/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 5/28/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 6/10/2024 | Conditional Approval | BOBBY KEY |
| HVAC-Rough | 6/10/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 6/10/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 6/24/2024 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 6/24/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 6/27/2024 | Corrections Issued | BOBBY KEY |
| Insulation | 6/27/2024 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 7/9/2024 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 7/9/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 7/9/2024 | Approved | BOBBY KEY |
| Insulation | 7/9/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 7/9/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 7/22/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 7/22/2024 | Approved | BOBBY KEY |
| Insulation | 7/22/2024 | Approved | BOBBY KEY |
| Shower Pan | 7/22/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 11/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 11/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 11/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 11/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 12/11/2024 | Approved | TEMISTOCLES CAAL |
| Final | 12/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/11/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 12/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Smoke Detectors | 12/11/2024 | Approved | TEMISTOCLES CAAL |
| Final | 2/3/2025 | OK to Issue CofO | TEMISTOCLES CAAL |