6712 S 2ND AVE 90043

Certificate Information: 6712 S 2ND AVE 90043

Application / Permit
22014-10000-02665
Plan Check / Job No.
B22LA10395
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN PROPOSED EXISTING 1-CAR GARAGE, GARAGE EXTENSION AND RECREATION ROOM TO BE CONVERTED TO ADU & BEDROOM AND BATHROOM ADDITION TO ADU. SCOPE OF WORK TO ALSO INCLUDE ATTACHED PATIO. DETACHED ADU CHECKED PER LAMC 12.22 A.22 (C)-(D) [ORDINANCE] AND PER WFPP
Permit Issued
Issued on 1/14/2023
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 SUNMIN LEE
Corrections Issued 6/10/2022 SUNMIN LEE
Applicant returned to address corrections 11/22/2022 SUNMIN LEE
Applicant returned to address corrections 12/20/2022 SUNMIN LEE
Applicant returned to address corrections 1/6/2023 MICHAEL LOPEZ
Plan Check Approved 1/9/2023 MICHAEL LOPEZ
Issued 1/14/2023 APPLICANT
CofO in Progress 8/27/2024 JOSE MACIAS
Permit Finaled 9/17/2024 DEROLD HAUFF
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/27/2022 WALLIE JONG
Roof/Waste drainage to street Cleared 6/27/2022 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/5/2022 WALLIE JONG
Sewer availability Cleared 7/5/2022 WALLIE JONG
Construction within easement Cleared 7/23/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Quiaot,, Florentino V; Lic. No.: C38659 412 W 231ST ST      CARSON, CA 90745

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/22/2023 Partial Approval STUART CHAPMAN
Deputy Drilled-In Anchors 9/28/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 9/29/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/29/2023 Approved ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 10/10/2023 Approved ENRIQUE MIRELES
Wood Frame 10/10/2023 Not Ready for Inspection ENRIQUE MIRELES
Deputy Wood Construction 10/24/2023 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 10/25/2023 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 10/25/2023 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 12/14/2023 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 1/10/2024 Approved ENRIQUE MIRELES
Insulation 1/10/2024 Approved ENRIQUE MIRELES
Drywall Nailing 1/22/2024 Approved JOSE MACIAS
Interior/Exterior Lathing 1/22/2024 Approved JOSE MACIAS
Shower Pan 2/16/2024 Approved JOSH MEISTER
ELECTRICAL-Final 5/24/2024 Corrections Issued JOSE MACIAS
Gas Test 5/24/2024 Approved JOSE MACIAS
ELECTRICAL-Final 5/30/2024 Corrections Issued JOSE MACIAS
Service/Power Release 5/30/2024 Approved JOSE MACIAS
ELECTRICAL-Final 6/26/2024 Approved JOSE MACIAS
HVAC-Final 6/26/2024 Corrections Issued JOSE MACIAS
PLUMBING-Final 6/26/2024 Approved JOSE MACIAS
Final 7/19/2024 Corrections Issued JOSE MACIAS
HVAC-Final 7/19/2024 Approved JOSE MACIAS
Final 8/5/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 8/5/2024 SGSOV Not Ready JOSE MACIAS
Smoke Detectors 8/5/2024 Approved JOSE MACIAS
Final 8/26/2024 OK to Issue CofO JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Approved JOSE MACIAS