319 W AVENUE 38 90065
Certificate Information: 319 W AVENUE 38 90065
- Application / Permit
- 22014-10000-02662
- Plan Check / Job No.
- B22LA10393
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT EXISTING DETACHED RECREATION ROOM INTO ONE ACCESSORY DWELLING UNITS PER ORDINANCE. ADU AREA = 1052 SF. ***SPRINKLERED PER NFPA 13 D***
- Permit Issued
- Issued on 2/6/2024
- Issuing Office
- Current Status
- CofO Issued on 9/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 7/7/2022 | MICHAEL LOPEZ |
| Corrections Issued | 7/18/2022 | MICHAEL LOPEZ |
| Quality Review Completed | 7/27/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 7/11/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 8/1/2023 | MICHAEL LOPEZ |
| Issued | 2/6/2024 | APPLICANT |
| CofO in Progress | 8/12/2024 | ALIZAH MAYAGOITIA |
| CofO Issued | 9/20/2024 | DEROLD HAUFF |
| Permit Finaled | 9/20/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/14/2022 | ROBERT HUGHES |
| Sewer availability | Cleared | 7/14/2022 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 7/19/2022 | ELAINE LEI |
| Address approval | Cleared | 7/20/2022 | ELAINE LEI |
| Specific Plan | Cleared | 7/25/2022 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 6/28/2023 | LAVEON RIDER |
Contact Information
| Contractor | Alltime Maintenance Inc; Lic. No.: 1033999-B | 2150 SACRAMENTO STREET LOS ANGELES, CA 90021 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/13/2024 | Conditional Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 2/22/2024 | Conditional Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 2/22/2024 | Partial Approval | LILIANA PORTILLO |
| Wood Frame | 3/12/2024 | Corrections Issued | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/11/2024 | Corrections Issued | OSVALDO PARAMO |
| Insulation | 4/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 4/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 5/22/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Wood Frame | 5/24/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/28/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 5/28/2024 | Approved | OSVALDO PARAMO |
| Insulation | 5/30/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 5/30/2024 | Partial Approval | OSVALDO PARAMO |
| Shower Pan | 5/30/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 6/12/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Drywall Nailing | 6/13/2024 | Approved | OSVALDO PARAMO |
| Shower Pan | 6/13/2024 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 6/20/2024 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 7/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Final | 7/30/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| HVAC-Final | 7/30/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 7/30/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 7/30/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 8/9/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Final | 8/12/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |