6649 N ORION AVE 91406
Certificate Information: 6649 N ORION AVE 91406
- Application / Permit
- 22014-10000-02626
- Plan Check / Job No.
- B22LA10250
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 1ST STORY REC. ROOM WITH GARAGE INTO AN ACCESSORY DWELLING UNIT (ADU) WITH 2ND FLOOR ADDITION WITH GARGE (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Current Status
- Issued on 9/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | AUNG SOE |
| Corrections Issued | 6/7/2022 | AUNG SOE |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Applicant returned to address corrections | 8/5/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 8/8/2024 | ALEXANDER JOO |
| Applicant returned to address corrections | 8/13/2024 | NEHEMIAS RAMOS |
| Plan Check Approved | 8/26/2024 | JOSE VELAZQUEZ |
| Issued | 9/11/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/13/2023 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 6/13/2023 | TAL SHEMEN |
| Certificate of Compliance | Cleared | 6/29/2023 | STEVEN WECHSLER |
| ZI | Cleared | 6/29/2023 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 6/30/2023 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 7/24/2023 | JOHN CONNEALLY |
| Sewer availability | Cleared | 12/13/2023 | JOHN LIN |
Contact Information
| Contractor | Snow Construction; Lic. No.: 1016716-B | 6647 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Wood Construction | 10/9/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 10/10/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 10/10/2024 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 10/22/2024 | Approved | RYAN SALAZAR |
| Wood Frame | 11/6/2024 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2024 | Partial Approval | RYAN SALAZAR |
| Deputy Wood Construction | 11/19/2024 | Conditional Approval | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/15/2025 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 1/15/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/15/2025 | Approved | RYAN SALAZAR |
| HVAC-Rough | 1/15/2025 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 1/15/2025 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 1/15/2025 | Approved | RYAN SALAZAR |
| Wood Frame | 1/15/2025 | Approved | RYAN SALAZAR |
| Sewer | 2/5/2025 | Approved | RYAN SALAZAR |
| Underground Mechanical | 2/5/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/26/2025 | Partial Approval | RYAN SALAZAR |
| Insulation | 3/3/2025 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/10/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 3/14/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/19/2025 | Approved | RYAN SALAZAR |
| Final | 1/22/2026 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 1/22/2026 | Approved | RYAN SALAZAR |
| MERV13>=Final | 1/22/2026 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/22/2026 | Approved | RYAN SALAZAR |