6649 N ORION AVE 91406

Certificate Information: 6649 N ORION AVE 91406

Application / Permit
22014-10000-02626
Plan Check / Job No.
B22LA10250
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 1ST STORY REC. ROOM WITH GARAGE INTO AN ACCESSORY DWELLING UNIT (ADU) WITH 2ND FLOOR ADDITION WITH GARGE (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 9/11/2024
Issuing Office
Current Status
Issued on 9/11/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/27/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 AUNG SOE
Corrections Issued 6/7/2022 AUNG SOE
Building Plans Picked Up 6/22/2022 APPLICANT
Applicant returned to address corrections 8/5/2024 JOHN MESIAS
Applicant returned to address corrections 8/8/2024 ALEXANDER JOO
Applicant returned to address corrections 8/13/2024 NEHEMIAS RAMOS
Plan Check Approved 8/26/2024 JOSE VELAZQUEZ
Issued 9/11/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/13/2023 TAL SHEMEN
Roof/Waste drainage to street Cleared 6/13/2023 TAL SHEMEN
Certificate of Compliance Cleared 6/29/2023 STEVEN WECHSLER
ZI Cleared 6/29/2023 STEVEN WECHSLER
Eng Process Fee Ord 176,300 Cleared 6/30/2023 TAL SHEMEN
Hydrant and Access approval Cleared 7/24/2023 JOHN CONNEALLY
Sewer availability Cleared 12/13/2023 JOHN LIN

Contact Information

Contractor Snow Construction; Lic. No.: 1016716-B 6647 ORION AVE      VAN NUYS, CA 91406
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 10/9/2024 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 10/10/2024 Partial Approval RYAN SALAZAR
PLUMBING-Rough 10/10/2024 Partial Approval RYAN SALAZAR
Footing/Foundation/Slab 10/22/2024 Approved RYAN SALAZAR
Wood Frame 11/6/2024 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/7/2024 Partial Approval RYAN SALAZAR
Deputy Wood Construction 11/19/2024 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 1/15/2025 Approved RYAN SALAZAR
ELECTRICAL-Rough 1/15/2025 Approved RYAN SALAZAR
Green Building Rough 1/15/2025 Approved RYAN SALAZAR
HVAC-Rough 1/15/2025 Approved RYAN SALAZAR
MERV13>=Rough 1/15/2025 Approved RYAN SALAZAR
PLUMBING-Rough 1/15/2025 Approved RYAN SALAZAR
Wood Frame 1/15/2025 Approved RYAN SALAZAR
Sewer 2/5/2025 Approved RYAN SALAZAR
Underground Mechanical 2/5/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/26/2025 Partial Approval RYAN SALAZAR
Insulation 3/3/2025 Approved RYAN SALAZAR
Drywall Nailing 3/10/2025 Approved RYAN SALAZAR
Shower Pan 3/14/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 3/19/2025 Approved RYAN SALAZAR
Final 1/22/2026 Corrections Issued RYAN SALAZAR
Green Building Final 1/22/2026 Approved RYAN SALAZAR
MERV13>=Final 1/22/2026 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/22/2026 SGSOV Approved RYAN SALAZAR
Smoke Detectors 1/22/2026 Approved RYAN SALAZAR