930 1/2 N FRIES AVE 90744

Certificate Information: 930 1/2 N FRIES AVE 90744

Application / Permit
22014-10000-02610
Plan Check / Job No.
B21LA24562
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
eplan CONVERT EXISTING GARAGE AND ADDITION TO ATTACHED ADU (930 1/2 N FRIES AVE) PER ORDINANCE AND LAMC 12.22 A 33(c)&(e) ATTACHED TO (E) DUPLEX (932 N FRIES AVE, #1-2)
Permit Issued
Issued on 12/11/2023
Issuing Office
Current Status
CofO Issued on 8/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/27/2022 ZAW HAN
Corrections Issued 6/1/2022 ZAW HAN
Applicant returned to address corrections 9/16/2022 ZAW HAN
Applicant returned to address corrections 11/9/2023 ZAW HAN
Plan Check Approved 12/3/2023 ZAW HAN
Issued 12/11/2023 APPLICANT
CofO in Progress 8/26/2024 EUGENE CASSIDY
Permit Finaled 8/26/2024 ANSON MAGLASANG
CofO Issued 8/26/2024 ANSON MAGLASANG
Permit Finaled 8/26/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 9/12/2022 ANA VILLA
Roof/Waste drainage to street Cleared 9/12/2022 ANA VILLA
Sewer availability Cleared 9/12/2022 ANA VILLA
"Q" conditions Cleared 9/13/2022 MAXFIELD VERMY
Clean Up Green Up Cleared 9/13/2022 MAXFIELD VERMY
ZA Case Cleared 9/13/2022 MAXFIELD VERMY
Eng Process Fee Ord 176,300 Cleared 11/6/2023 KHAING AYE
Tenant Habitability Plan Cleared 11/7/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/21/2024 Approved EUGENE CASSIDY
METHANE-Barrier 2/21/2024 Approved EUGENE CASSIDY
METHANE-Subgrade 2/21/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 3/13/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/17/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/17/2024 Approved EUGENE CASSIDY
HVAC-Rough 4/17/2024 Partial Approval EUGENE CASSIDY
METHANE-Rough 4/17/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 4/17/2024 Approved EUGENE CASSIDY
Insulation 5/1/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/1/2024 Approved EUGENE CASSIDY
Drywall Nailing 5/9/2024 Approved EUGENE CASSIDY
Final 7/2/2024 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/2/2024 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 7/2/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/23/2024 Approved EUGENE CASSIDY
Final 8/23/2024 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 8/23/2024 Approved EUGENE CASSIDY
PLUMBING-Final 8/23/2024 Approved EUGENE CASSIDY