3254 S INGLEWOOD BLVD 90066

Certificate Information: 3254 S INGLEWOOD BLVD 90066

Application / Permit
22014-10000-02606
Plan Check / Job No.
B22LA10139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
eplan Addition and Renovation to an existing single family dwelling w/att garage.
Permit Issued
Issued on 2/13/2023
Issuing Office
Current Status
CofO Issued on 10/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2022 APPLICANT
Assigned to Plan Check Engineer 6/30/2022 ADRIANA LOPEZ
Corrections Issued 7/12/2022 ADRIANA LOPEZ
Quality Review Completed 7/12/2022 GARO TELMI
Applicant returned to address corrections 2/8/2023 ADRIANA LOPEZ
Plan Check Approved 2/9/2023 ADRIANA LOPEZ
Issued 2/13/2023 APPLICANT
CofO in Progress 10/30/2023 JESUS PINEDA
Permit Finaled 10/31/2023 DANIEL ORRANTE
CofO Issued 10/31/2023 DANIEL ORRANTE
Permit Finaled 10/31/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 7/29/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 8/18/2022 DINAH GARIN
Grading Pre-Inspection Cleared 10/3/2022 KIRK LINKLATER
Specific Plan Cleared 11/20/2022 PEDRO AYALA
Low Impact Development Cleared 12/23/2022 MITESH PATEL
Roof/Waste drainage to street Cleared 1/3/2023 AHMED AMARRAGY
GPI Written Notices Cleared 2/11/2023 ADRIANA LOPEZ

Contact Information

Contractor Karma Remodel & Development Inc; Lic. No.: 875130-B       ,
Engineer Polon,, Gordon Leonard; Lic. No.: C28564 709 19TH STREET      SANTA MONICA, CA 90402
Engineer Polon,, Gordon Leonard; Lic. No.: NA28564       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/22/2023 Partial Approval JOHNNY MIRANDA
Underground Mechanical 3/6/2023 Corrections Issued JOHNNY MIRANDA
Underground Mechanical 3/7/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 3/9/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 3/14/2023 Partial Approval CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Partial Approval JOHNNY MIRANDA
Wood Frame 3/28/2023 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 4/7/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/7/2023 Partial Approval JOHNNY MIRANDA
Insulation 4/7/2023 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 4/7/2023 Partial Approval JOHNNY MIRANDA
Wood Frame 4/7/2023 Not Ready for Inspection JOHNNY MIRANDA
Drywall Nailing 4/13/2023 Partial Approval HERBERT GIRON
Interior/Exterior Lathing 4/19/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/1/2023 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 5/19/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/19/2023 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/19/2023 Partial Approval JOHNNY MIRANDA
Green Building Rough 5/19/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 5/19/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/19/2023 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/26/2023 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/26/2023 Partial Approval JOHNNY MIRANDA
Insulation 5/30/2023 Approved JOHNNY MIRANDA
Shower Pan 5/31/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 6/5/2023 Approved JOHNNY MIRANDA
Drywall Nailing 6/7/2023 Approved EVAN COOPER
Green Building Rough 6/7/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 8/10/2023 Approved JESUS PINEDA
Final 8/10/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 8/10/2023 Approved JESUS PINEDA
Green Building Final 8/10/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/10/2023 SGSOV Approved JESUS PINEDA
Smoke Detectors 8/10/2023 Approved JESUS PINEDA
ELECTRICAL-Final 10/26/2023 Approved JESUS PINEDA
Final 10/26/2023 OK to Issue CofO JESUS PINEDA
HVAC-Final 10/26/2023 Approved JESUS PINEDA
PLUMBING-Final 10/26/2023 Approved JESUS PINEDA