7718 N SATSUMA AVE 91352
Certificate Information: 7718 N SATSUMA AVE 91352
- Application / Permit
- 22014-10000-02591
- Plan Check / Job No.
- B22LA10086
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21x20 ADDITION AND NEW PATIO COVER AT REAR TO EXISTING ONE STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE
- Permit Issued
- Issued on 11/29/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | AUNG SOE |
| Corrections Issued | 6/2/2022 | AUNG SOE |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| Plan Check Approved | 11/22/2022 | LUKE GONZALES |
| Issued | 11/29/2022 | APPLICANT |
| CofO in Progress | 1/24/2024 | MATTHEW NELSON |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/7/2022 | CHRIS CHAHBAZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/8/2022 | CHRIS CHAHBAZ |
| Hydrant and Access approval | Cleared | 7/7/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 11/9/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 11/21/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/10/2023 | Conditional Approval | MATTHEW NELSON |
| Footing/Foundation/Slab | 2/15/2023 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 3/29/2023 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 3/29/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 3/29/2023 | Approved | MATTHEW NELSON |
| Deputy Wood Construction | 3/30/2023 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 4/3/2023 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 4/28/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/28/2023 | Approved | MATTHEW NELSON |
| Insulation | 5/4/2023 | Approved | WILLIAM WREN |
| Drywall Nailing | 5/10/2023 | Approved | MATTHEW NELSON |
| Final | 1/17/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 1/17/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 1/17/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 1/23/2024 | OK to Issue CofO | MATTHEW NELSON |