11060-11062 N ONEIDA AVE 91340

Certificate Information: 11060-11062 N ONEIDA AVE 91340

Application / Permit
22014-10000-02586
Plan Check / Job No.
B22LA10067
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT AND ADDITION 1ST FLOOR GARAGE INTO A.D.U. PER LAMC 12.22 A.33 (c) (d) INCLUDES REMODEL IN (E) SFD.
Permit Issued
Issued on 6/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 6/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2022 APPLICANT
Assigned to Plan Check Engineer 5/31/2022 LAWRENCE QUIRANTE
Corrections Issued 5/31/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 6/7/2022 APPLICANT
Applicant returned to address corrections 9/28/2022 RACHEL BEYENE
Applicant returned to address corrections 10/13/2022 KHUONG TRUONG
Plan Check Approved 10/14/2022 MINA HABILI
Issued 6/14/2023 APPLICANT
CofO in Progress 5/23/2025 JENNIFER RABUCHIN
Permit Finaled 6/3/2025 RUBEN SALAS
CofO Issued 6/3/2025 RUBEN SALAS
Permit Finaled 6/3/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/23/2022 COLIN LOREDO
Roof/Waste drainage to street Cleared 8/23/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 8/25/2022 COLIN LOREDO
Sewer availability Cleared 8/25/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/5/2023 Partial Approval JENNIFER RABUCHIN
METHANE-Barrier 7/5/2023 Approved JENNIFER RABUCHIN
METHANE-Subgrade 7/5/2023 Approved JENNIFER RABUCHIN
Pre-Inspection 7/5/2023 Approved JENNIFER RABUCHIN
Sewer 7/21/2023 Approved JENNIFER RABUCHIN
Wood Frame 7/21/2023 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 8/22/2023 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 8/22/2023 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 8/22/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 9/7/2023 Approved JENNIFER RABUCHIN
Green Building Rough 9/7/2023 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Rough 9/7/2023 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/22/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 9/22/2023 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 9/22/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 10/6/2023 Partial Approval JENNIFER RABUCHIN
Green Building Rough 10/6/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/6/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 10/6/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/2/2023 Corrections Issued JENNIFER RABUCHIN
Gas Test 11/2/2023 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 11/2/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 11/16/2023 Partial Approval JENNIFER RABUCHIN
Gas Test 11/16/2023 Partial Approval JENNIFER RABUCHIN
Underground Mechanical 11/16/2023 Partial Approval JENNIFER RABUCHIN
Service/Power Release 12/12/2023 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 12/29/2023 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/29/2023 Approved JENNIFER RABUCHIN
Insulation 12/29/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 2/15/2024 No Access for Inspection SALVADOR MARTINEZ
Shower Pan 2/15/2024 No Access for Inspection SALVADOR MARTINEZ
Drywall Nailing 2/16/2024 Approved SALVADOR MARTINEZ
Shower Pan 2/16/2024 Approved SALVADOR MARTINEZ
Interior/Exterior Lathing 3/20/2024 Approved JENNIFER RABUCHIN
Service/Power Release 3/20/2024 Corrections Issued JENNIFER RABUCHIN
Smoke Detectors 3/20/2024 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 5/15/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/16/2024 Corrections Issued JENNIFER RABUCHIN
Final 12/16/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 12/16/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 12/16/2024 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/23/2025 Partial Approval JENNIFER RABUCHIN
Final 1/23/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/23/2025 Approved JENNIFER RABUCHIN
Non Compliance 1/23/2025 Not Required JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/23/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 1/23/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/14/2025 Approved JENNIFER RABUCHIN
Final 4/14/2025 Not Ready for Inspection JENNIFER RABUCHIN
Final 5/23/2025 OK to Issue CofO JENNIFER RABUCHIN