3513 1/2 W BELLEVUE AVE 90026
Certificate Information: 3513 1/2 W BELLEVUE AVE 90026
- Application / Permit
- 22014-10000-02581
- Plan Check / Job No.
- B22LA10042
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Conversion of (E) storage shed into (N) ADU and Adding 408 SQ. FT. of floor area for Total of 696 SQ. FT. of ADU
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2022 | HANS SANTIAGO |
| Corrections Issued | 5/28/2022 | HANS SANTIAGO |
| Applicant returned to address corrections | 7/13/2022 | HANS SANTIAGO |
| Plan Check Approved | 7/21/2022 | ANDREW SANTIAGO |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 8/30/2023 | FREDDIE RIVERA |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2022 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 6/3/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 6/6/2022 | STEVE MELGAR |
| Grading Pre-Inspection | Cleared | 6/8/2022 | ALEXANDER HELFER |
| Hydrant and Access approval | Cleared | 7/9/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Martirossyan,, Armen; Lic. No.: NA64223 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/9/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 1/25/2023 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 1/25/2023 | Approved | FREDDIE RIVERA |
| Insulation | 1/25/2023 | Partial Approval | FREDDIE RIVERA |
| PLUMBING-Rough | 1/25/2023 | Approved | FREDDIE RIVERA |
| Wood Frame | 1/25/2023 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 5/1/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 5/1/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/1/2023 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/1/2023 | Approved | FREDDIE RIVERA |
| Insulation | 5/1/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 5/2/2023 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/2/2023 | Approved | FREDDIE RIVERA |
| Insulation | 5/2/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 6/6/2023 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 6/6/2023 | Approved | FREDDIE RIVERA |
| Wood Frame | 6/6/2023 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 7/11/2023 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 7/11/2023 | Approved | FREDDIE RIVERA |
| Final | 7/11/2023 | Corrections Issued | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/11/2023 | Approved | FREDDIE RIVERA |
| Green Building Final | 7/11/2023 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 7/11/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Final | 7/11/2023 | Approved | FREDDIE RIVERA |
| MERV13>=Rough | 7/11/2023 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 7/11/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/11/2023 | SGSOV Approved | FREDDIE RIVERA |
| Smoke Detectors | 7/11/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 7/18/2023 | Partial Inspection | FREDDIE RIVERA |
| Green Building Final | 7/18/2023 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 7/18/2023 | Approved | FREDDIE RIVERA |
| Final | 8/24/2023 | Conditional Approval | FREDDIE RIVERA |
| Green Building Final | 8/24/2023 | Approved | FREDDIE RIVERA |
| Final | 8/30/2023 | OK to Issue CofO | FREDDIE RIVERA |