3415 E ALICE ST 90065

Certificate Information: 3415 E ALICE ST 90065

Application / Permit
22014-10000-02570
Plan Check / Job No.
B22LA10024
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Conversion of the REC Room to ADU (645 sq. ft.) "COMPLY WITH DEPARTMENT ORDER effective date 04/19/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 7/7/2022
Issuing Office
Current Status
CofO Issued on 3/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/27/2022 SUNMIN LEE
Corrections Issued 5/31/2022 SUNMIN LEE
Applicant returned to address corrections 6/21/2022 SUNMIN LEE
Plan Check Approved 7/1/2022 SUNMIN LEE
Issued 7/7/2022 APPLICANT
CofO in Progress 2/22/2024 JACOB SEGURA
Permit Finaled 3/27/2024 DANIEL SANCHEZ
CofO Issued 3/27/2024 DANIEL SANCHEZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/6/2022 KIRK LINKLATER
Address approval Cleared 6/21/2022 JEANIE LAM
Roof/Waste drainage to street Cleared 6/21/2022 JEANIE LAM
Sewer availability Cleared 6/21/2022 JEANIE LAM
ZI Cleared 6/21/2022 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 6/22/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Zhuang,, Wenbin; Lic. No.: S5236 205 S CHAPEL AVE #D-1      ALHAMBRA, CA 91801

Inspector Information

THOMAS WILLIS, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JEFFREY CHRISTIAN, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
FERMIN RUBIO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
JACOB SEGURA, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
CLAUDIO MORENO, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI
MARK RUDE, (213) 252-3038 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/8/2022 Approved JAVIER RAMOS SR
ELECTRICAL-Rough 1/5/2023 Partial Approval JAVIER RAMOS SR
PLUMBING-Rough 1/5/2023 Approved JAVIER RAMOS SR
Insulation 1/9/2023 No Access for Inspection JAVIER RAMOS SR
Insulation 1/12/2023 Partial Approval JAVIER RAMOS SR
Insulation 2/15/2023 Approved JAVIER RAMOS SR
Drywall Nailing 2/23/2023 Approved JAVIER RAMOS SR
Floor/Roof Diaphrgm/Shear Wall 2/23/2023 Approved JAVIER RAMOS SR
Sewer 2/23/2023 Approved JAVIER RAMOS SR
Shower Pan 2/23/2023 Approved JAVIER RAMOS SR
Underground Mechanical 2/23/2023 Approved JAVIER RAMOS SR
BUILDING-Rough-Frame 3/20/2023 Approved JAVIER RAMOS SR
Final 3/20/2023 Not Ready for Inspection JAVIER RAMOS SR
Footing/Foundation/Slab 3/20/2023 Approved JAVIER RAMOS SR
Interior/Exterior Lathing 3/20/2023 Approved JAVIER RAMOS SR
SGSOV-Seismic Gas S/O Valve 3/20/2023 SGSOV Not Ready JAVIER RAMOS SR
Smoke Detectors 3/20/2023 Not Ready for Inspection JAVIER RAMOS SR
ELECTRICAL-Rough 4/3/2023 Approved JAVIER RAMOS SR
HVAC-Rough 4/3/2023 Approved JAVIER RAMOS SR
PLUMBING-Rough 4/3/2023 Approved JAVIER RAMOS SR
Final 7/11/2023 Not Ready for Inspection JAVIER RAMOS SR
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Not Ready JAVIER RAMOS SR
Smoke Detectors 7/11/2023 Not Ready for Inspection JAVIER RAMOS SR
Final 8/28/2023 Not Ready for Inspection JAVIER RAMOS SR
Gas Test 8/28/2023 Approved JAVIER RAMOS SR
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved JAVIER RAMOS SR
Smoke Detectors 8/28/2023 Approved JAVIER RAMOS SR
Final 10/13/2023 OK to Issue CofO JACOB SEGURA