4611 N ELLENWOOD DR 90041
Certificate Information: 4611 N ELLENWOOD DR 90041
- Application / Permit
- 22014-10000-02558
- Plan Check / Job No.
- B22LA09978
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADITION AT 1ST & 2ND FLOOR
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | TSE MING HUANG |
| Corrections Issued | 6/10/2022 | TSE MING HUANG |
| Quality Review Completed | 6/15/2022 | KEN GILL |
| Building Plans Picked Up | 6/29/2022 | APPLICANT |
| Plan Check Approved | 10/26/2022 | TSE MING HUANG |
| Issued | 11/1/2022 | APPLICANT |
| CofO in Progress | 11/29/2023 | BRIAN SULLIVAN |
| No Progress | 12/4/2023 | SCOTT FINNILA |
| CofO in Progress | 1/17/2024 | ROY SPAULDING |
| No Progress | 1/17/2024 | ROY SPAULDING |
| Permit Finaled | 1/26/2026 | DEROLD HAUFF |
| CofO Issued | 1/26/2026 | DEROLD HAUFF |
| Permit Finaled | 1/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/9/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 7/12/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 7/12/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 10/11/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/15/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 10/26/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/3/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/19/2023 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2023 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Partial Approval | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 6/12/2023 | Corrections Issued | OSVALDO PARAMO |
| Deputy Wood Construction | 6/14/2023 | Conditional Approval | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Approved | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 6/20/2023 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 6/20/2023 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 7/7/2023 | Partial Approval | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/7/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Wood Frame | 8/23/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 8/28/2023 | Corrections Issued | JOSH MEISTER |
| Insulation | 9/1/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/7/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/13/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Shower Pan | 9/13/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 9/19/2023 | Approved | CRAIG VAUGHAN |
| Final | 11/14/2023 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 11/14/2023 | Partial Approval | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | ROY SPAULDING |
| Smoke Detectors | 11/14/2023 | Approved | ROY SPAULDING |
| Final | 11/28/2023 | OK to Issue CofO | BRIAN SULLIVAN |
| Green Building Final | 11/28/2023 | Approved | BRIAN SULLIVAN |
| Special/Order Compliance | 12/22/2025 | Corrections Issued | DAVID WILLIAMS |