1028 S PLEASANT VIEW AVE 90291
Certificate Information: 1028 S PLEASANT VIEW AVE 90291
- Application / Permit
- 22014-10000-02556
- Plan Check / Job No.
- B22LA09963
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan ADDITION TO (E) TO SFD AND MAJOR REMODEL 1 OF 2
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Current Status
- CofO Issued on 1/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2022 | ADRIANA LOPEZ |
| Corrections Issued | 7/5/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 7/6/2022 | GARO TELMI |
| Applicant returned to address corrections | 9/28/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 10/14/2022 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 11/1/2022 | ADRIANA LOPEZ |
| Plan Check Approved | 11/22/2022 | ADRIANA LOPEZ |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 1/8/2024 | HERBERT GIRON |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
| CofO Issued | 1/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/4/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | HISASHI KOBAYAKAWA |
| Low Impact Development | Cleared | 9/8/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 9/9/2022 | DINAH GARIN |
| Coastal Zone | Cleared | 9/13/2022 | DANIEL CORONADO |
| Coastal Zone | Cleared | 9/13/2022 | DANIEL CORONADO |
| Specific Plan | Cleared | 9/14/2022 | FREDDY GARCIA |
| ZI | Cleared | 9/16/2022 | JULIET OH |
Contact Information
| Architect | Jantzen,, Christof; Lic. No.: C29896 | 40 18TH AVENUE #1 VENICE, CA 90291 |
| Contractor | Md Electrical Services Inc; Lic. No.: 972173-B | , |
| Engineer | Herrera,, Edgar E; Lic. No.: C67603 | 1929 GREENLEAF DR WEST COVINA, CA 91792 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2023 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 2/16/2023 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 3/24/2023 | Corrections Issued | EVAN COOPER |
| Deputy Reinf. Concrete | 3/28/2023 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 4/6/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2023 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 6/14/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 6/14/2023 | Approved | EVAN COOPER |
| Deputy Wood Construction | 6/16/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/16/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2023 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 6/29/2023 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 7/10/2023 | Partial Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 8/15/2023 | Corrections Issued | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/15/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | HERBERT GIRON |
| Insulation | 9/13/2023 | Approved | KENNETH NAGLE |
| Shower Pan | 9/13/2023 | Approved | KENNETH NAGLE |
| Drywall Nailing | 9/25/2023 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 9/25/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/15/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 12/15/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 12/18/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 12/20/2023 | Approved | HERBERT GIRON |
| HVAC-Rough | 12/20/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 12/20/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/21/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 12/21/2023 | Approved | HERBERT GIRON |
| Final | 1/8/2024 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 1/8/2024 | Approved | HERBERT GIRON |
| Smoke Detectors | 1/8/2024 | Approved | HERBERT GIRON |