1849 S REDONDO BLVD 90019
Certificate Information: 1849 S REDONDO BLVD 90019
- Application / Permit
- 22014-10000-02530
- Plan Check / Job No.
- B22LA09867
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH ADDITION. COMPLY WITH DEPARTMENT ORDER effective date 03/29/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS #950989.
- Permit Issued
- Issued on 9/7/2022
- Issuing Office
- Current Status
- CofO Issued on 12/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/27/2022 | GEORGE ALVAREZ |
| Corrections Issued | 5/29/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 6/8/2022 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 6/30/2022 | GEORGE ALVAREZ |
| Plan Check Approved | 8/24/2022 | GEORGE ALVAREZ |
| Issued | 9/7/2022 | APPLICANT |
| CofO in Progress | 10/23/2023 | WILLIAM MICHALAK |
| CofO in Progress | 11/30/2023 | WILLIAM MICHALAK |
| Permit Finaled | 12/6/2023 | BRUCE TODD |
| CofO Issued | 12/6/2023 | BRUCE TODD |
| Permit Finaled | 12/6/2023 | BRUCE TODD |
Permit Application Clearance Information
| Address approval | Cleared | 6/3/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 6/14/2022 | AMAAN MALIK |
| Low Impact Development | Cleared | 7/7/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 7/12/2022 | AMAAN MALIK |
| Construction near power lines | Cleared | 8/19/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/19/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CORRAL, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| DONALD WONG, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM DOEPPING, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM MICHALAK, (213) 252-3964 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/5/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| Underground Mechanical | 1/5/2023 | Partial Approval | WILLIAM MICHALAK |
| Excavation/Setback/Form/Re-Bar | 1/20/2023 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 1/20/2023 | Corrections Issued | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | WILLIAM MICHALAK |
| ELECTRICAL-Rough | 3/8/2023 | Approved | WILLIAM MICHALAK |
| HVAC-Rough | 3/8/2023 | Conditional Approval | WILLIAM MICHALAK |
| PLUMBING-Rough | 3/8/2023 | Approved | WILLIAM MICHALAK |
| BUILDING-Rough-Frame | 3/24/2023 | Approved | WILLIAM MICHALAK |
| Insulation | 3/24/2023 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 3/24/2023 | Approved | WILLIAM MICHALAK |
| Shower Pan | 3/24/2023 | Approved | WILLIAM MICHALAK |
| Drywall Nailing | 3/29/2023 | Approved | WILLIAM MICHALAK |
| Interior/Exterior Lathing | 3/29/2023 | Approved | WILLIAM MICHALAK |
| ELECTRICAL-Final | 8/17/2023 | Corrections Issued | GLEN RAND |
| Final | 8/17/2023 | Corrections Issued | GLEN RAND |
| Footing/Foundation/Slab | 8/17/2023 | Conditional Approval | GLEN RAND |
| Gas Test | 8/17/2023 | Corrections Issued | GLEN RAND |
| HVAC-Final | 8/17/2023 | Corrections Issued | GLEN RAND |
| PLUMBING-Final | 8/17/2023 | Approved | GLEN RAND |
| SGSOV-Seismic Gas S/O Valve | 8/17/2023 | SGSOV Approved | GLEN RAND |
| Smoke Detectors | 8/17/2023 | Approved | GLEN RAND |
| ELECTRICAL-Final | 8/31/2023 | Corrections Issued | WILLIAM MICHALAK |
| Final | 8/31/2023 | Corrections Issued | WILLIAM MICHALAK |
| Footing/Foundation/Slab | 8/31/2023 | Approved | WILLIAM MICHALAK |
| PLUMBING-Final | 8/31/2023 | Approved | WILLIAM MICHALAK |
| Service/Power Release | 8/31/2023 | Corrections Issued | WILLIAM MICHALAK |
| Final | 9/21/2023 | Conditional Approval | WILLIAM MICHALAK |
| ELECTRICAL-Final | 11/30/2023 | Approved | WILLIAM MICHALAK |
| Final | 11/30/2023 | OK to Issue CofO | WILLIAM MICHALAK |