7312 S 5TH AVE 90043
Certificate Information: 7312 S 5TH AVE 90043
- Application / Permit
- 22014-10000-02528
- Plan Check / Job No.
- B22LA09864
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE INTO A NEW ADU WITH ADDITION PER LAMC 12.22 A.33 (C)(D)
- Permit Issued
- Issued on 2/8/2023
- Issuing Office
- Metro
- Current Status
- Issued on 2/8/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2022 | KHUONG TRUONG |
| Corrections Issued | 5/28/2022 | KHUONG TRUONG |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| Applicant returned to address corrections | 8/11/2022 | MINA HABILI |
| Plan Check Approved | 8/25/2022 | ADAM HEGAZI |
| Issued | 2/8/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/25/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 7/25/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 7/25/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/3/2023 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/7/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 4/7/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 4/10/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 4/11/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/14/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/19/2023 | Approved | ENRIQUE MIRELES |
| Final | 6/20/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/20/2023 | Approved | ENRIQUE MIRELES |
| Green Building Final | 6/20/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/20/2023 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 6/20/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Final | 7/3/2023 | Corrections Issued | ENRIQUE MIRELES |
| Final | 5/21/2024 | No Access for Inspection | JOSE MACIAS |
| Deputy Drilled-In Anchors | 9/25/2024 | No Access for Inspection | AMIR NAZARIAN |
| Footing/Foundation/Slab | 9/27/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 9/27/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2024 | Approved | AMIR NAZARIAN |
| Interior/Exterior Lathing | 10/2/2024 | Approved | AMIR NAZARIAN |
| Final | 1/27/2026 | Corrections Issued | SALVADOR MARTINEZ |