3947 N EUREKA DR 91604
Certificate Information: 3947 N EUREKA DR 91604
- Application / Permit
- 22014-10000-02489
- Plan Check / Job No.
- B22LA09689
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel of (E) single family dwelling
- Permit Issued
- Issued on 6/30/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2022 | ADAM HEGAZI |
| Corrections Issued | 5/25/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 6/21/2022 | APPLICANT |
| Plan Check Approved | 7/8/2022 | SHANGQIN XIE |
| Issued | 6/30/2023 | APPLICANT |
| CofO in Progress | 4/10/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
| CofO Issued | 4/24/2025 | RUBEN SALAS |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | MEGAN GODINEZ |
| Roof/Waste drainage to street | Cleared | 6/21/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 6/21/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 6/21/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 6/21/2022 | MEGAN GODINEZ |
| Grading Pre-Inspection | Cleared | 6/24/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/18/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 6/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/28/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/19/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Partial Approval | JACK KARGODORIAN |
| Insulation | 7/29/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| HVAC-Rough | 10/4/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 10/11/2024 | Conditional Approval | JUAN VALENZUELA |
| Deputy Wood Construction | 10/11/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/4/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/4/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 11/4/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 11/4/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 11/8/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 11/20/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 11/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 11/20/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 11/25/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Insulation | 1/21/2025 | Approved | RUBEN SALAS |
| Drywall Nailing | 2/10/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 2/10/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/2/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Green Building Final | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/2/2025 | SGSOV Not Ready | CHRISTOPHE COCHRAN |
| Smoke Detectors | 4/2/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 4/10/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |