4645 N WAWONA ST 90065

Certificate Information: 4645 N WAWONA ST 90065

Application / Permit
22014-10000-02483
Plan Check / Job No.
B22LA09671
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to existing single family residence.
Permit Issued
Issued on 4/27/2023
Issuing Office
Current Status
CofO Issued on 10/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2022 APPLICANT
Assigned to Plan Check Engineer 5/26/2022 CARLOS MONTES
Corrections Issued 5/27/2022 CARLOS MONTES
Applicant returned to address corrections 10/25/2022 DANIEL YIP
Applicant returned to address corrections 4/19/2023 MICHAEL LOPEZ
Applicant returned to address corrections 4/20/2023 MICHAEL LOPEZ
Plan Check Approved 4/24/2023 KEVIN MORALES
Issued 4/27/2023 APPLICANT
CofO in Progress 10/9/2024 ROY SPAULDING
CofO in Progress 10/11/2024 ROY SPAULDING
Permit Finaled 10/16/2024 RUBEN SALAS
CofO Issued 10/16/2024 RUBEN SALAS
Permit Finaled 10/16/2024 RUBEN SALAS

Permit Application Clearance Information

Miscellaneous Cleared 6/9/2022 RYAN LY
ZA Case Cleared 6/9/2022 RYAN LY
BHO/Hillside ordinance Cleared 6/10/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 6/10/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 6/10/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 6/10/2022 JEANETTE VONG
BHO/Hillside ordinance Cleared 6/10/2022 JEANETTE VONG
Sewer availability Cleared 6/10/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 7/7/2022 JEANETTE VONG
Distance to fire station Cleared 9/1/2022 LAVEON RIDER
Hydrant and Access approval Cleared 9/1/2022 LAVEON RIDER
Low Impact Development Cleared 3/29/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 4/10/2023 STEVE MELGAR
GPI Written Notices Cleared 4/20/2023 CARLOS MONTES
Grading Pre-Inspection Cleared 4/20/2023 ROBERT HUGHES

Contact Information

Contractor Creative Innovation Developers Inc; Lic. No.: 1035641-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/28/2023 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/4/2023 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 8/23/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 8/23/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 8/24/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 8/24/2023 Not Ready for Inspection CRAIG VAUGHAN
MERV13>=Rough 8/24/2023 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 8/28/2023 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 8/28/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/26/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 11/6/2023 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval CRAIG VAUGHAN
HVAC-Rough 11/6/2023 Corrections Issued CRAIG VAUGHAN
BUILDING-Rough-Frame 11/30/2023 Corrections Issued CRAIG VAUGHAN
Green Building Rough 11/30/2023 Approved CRAIG VAUGHAN
HVAC-Rough 11/30/2023 Corrections Issued CRAIG VAUGHAN
MERV13>=Rough 11/30/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 11/30/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 12/5/2023 Corrections Issued CRAIG VAUGHAN
PLUMBING-Rough 12/5/2023 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/27/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/27/2023 Partial Approval JOAQUIN GREENOUGH
HVAC-Rough 12/27/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Insulation 12/27/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Interior/Exterior Lathing 12/27/2023 Partial Approval JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/29/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 12/29/2023 Approved JOAQUIN GREENOUGH
Insulation 12/29/2023 Approved JOAQUIN GREENOUGH
Drywall Nailing 1/3/2024 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 1/3/2024 Approved CRAIG VAUGHAN
Final 6/27/2024 Corrections Issued BRIAN SULLIVAN
Green Building Final 6/27/2024 Approved BRIAN SULLIVAN
MERV13>=Final 6/27/2024 Approved BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/27/2024 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 6/27/2024 Corrections Issued BRIAN SULLIVAN
Final 10/8/2024 OK to Issue CofO ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 10/8/2024 Approved ROY SPAULDING
Final 10/10/2024 OK to Issue CofO ROY SPAULDING