1502 W 214TH ST 90501
Certificate Information: 1502 W 214TH ST 90501
- Application / Permit
- 22014-10000-02457
- Plan Check / Job No.
- B22LA09583
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1ST FLOOR AND SECOND FLOOR ADDITION TO (E) 1-STORY SFD WITH INTERIOR AND EXTERIOR STRUCTURAL REMODE. -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 6/16/2025
- Issuing Office
- Metro
- Current Status
- Issued on 6/16/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/10/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 6/16/2022 | SAI KHUM |
| Building Plans Picked Up | 6/22/2022 | APPLICANT |
| Applicant returned to address corrections | 8/17/2022 | MAHNAZ NOURHASHEMI |
| Applicant returned to address corrections | 6/7/2023 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 6/3/2025 | MAHNAZ NOURHASHEMI |
| Issued | 6/16/2025 | APPLICANT |
Permit Application Clearance Information
| Highway dedication | Cleared | 1/19/2024 | KHAING AYE |
| Permit | Cleared | 1/19/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 4/10/2024 | KHAING AYE |
| Low Impact Development | Cleared | 8/5/2024 | MITESH PATEL |
| Sewer availability | Cleared | 8/7/2024 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 9/12/2024 | JILVER MAZARIEGOS |
| Trees in Parkway | Cleared | 3/25/2025 | ADALBERTO VERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Namvar,, Mohammad Alipour; Lic. No.: C39797 | 231 VISTA DEL MAR STE D REDONDO BEACH, CA 90277 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/7/2025 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 7/7/2025 | Partial Approval | JOHN KLARIN |
| Footing/Foundation/Slab | 7/9/2025 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/11/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/8/2025 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 8/8/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Special/Order Compliance | 8/8/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/28/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 8/28/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/18/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 9/18/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 9/18/2025 | Approved | EUGENE CASSIDY |
| Insulation | 10/30/2025 | Corrections Issued | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/14/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/14/2025 | Approved | EUGENE CASSIDY |
| Green Building Rough | 11/14/2025 | Approved | EUGENE CASSIDY |
| Insulation | 11/14/2025 | Approved | EUGENE CASSIDY |
| Shower Pan | 11/14/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 1/9/2026 | Approved | EUGENE CASSIDY |
| Excavation/Setback/Form/Re-Bar | 4/17/2026 | Not Ready for Inspection | EUGENE CASSIDY |