8025 S ALVERSTONE AVE 90045
Certificate Information: 8025 S ALVERSTONE AVE 90045
- Application / Permit
- 22014-10000-02448
- Plan Check / Job No.
- B22LA09558
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO (E) 1-STORY SFD AND (N) ROOF DECK
- Permit Issued
- Issued on 8/9/2022
- Issuing Office
- Current Status
- CofO Issued on 2/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/16/2022 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 6/24/2022 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/1/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 7/8/2022 | APPLICANT |
| Plan Check Approved | 8/9/2022 | MAHNAZ NOURHASHEMI |
| Plan Check Approved | 8/9/2022 | MAHNAZ NOURHASHEMI |
| Issued | 8/9/2022 | APPLICANT |
| CofO in Progress | 2/3/2023 | HERBERT GIRON |
| Permit Finaled | 2/8/2023 | DANIEL ORRANTE |
| CofO Issued | 2/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2022 | JENSON LEE |
| Roof/Waste drainage to street | Cleared | 7/20/2022 | JENSON LEE |
Contact Information
| Contractor | Construction Masters; Lic. No.: 762655-B | 18075 VENTURA BLVD STE 135 ENCINO, CA 91316 |
| Engineer | Khazra,, Afshin; Lic. No.: C50250 | 22855 PAUL REVERE DR CALABASAS, CA 91302 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/29/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 8/29/2022 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 9/6/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 9/6/2022 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 9/8/2022 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 9/8/2022 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/13/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 9/13/2022 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Drilled-In Anchors | 9/14/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 9/15/2022 | Partial Approval | HERBERT GIRON |
| Insulation | 9/15/2022 | Partial Approval | HERBERT GIRON |
| Deputy Wood Construction | 9/19/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 9/29/2022 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Wood Construction | 9/29/2022 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 9/29/2022 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/3/2022 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 10/3/2022 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 10/13/2022 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Approved | HERBERT GIRON |
| Green Building Rough | 10/19/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 10/19/2022 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 10/19/2022 | Approved | HERBERT GIRON |
| Deputy Wood Construction | 10/24/2022 | Conditional Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 10/25/2022 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 10/25/2022 | Approved | HERBERT GIRON |
| Insulation | 10/31/2022 | Approved | HERBERT GIRON |
| Drywall Nailing | 11/3/2022 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 12/13/2022 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 12/13/2022 | Approved | HERBERT GIRON |
| Final | 12/13/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 12/13/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 12/13/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 12/13/2022 | Approved | HERBERT GIRON |
| Final | 1/19/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 1/19/2023 | Approved | HERBERT GIRON |
| Final | 2/2/2023 | OK to Issue CofO | HERBERT GIRON |