5141 N VARNA AVE 91423
Certificate Information: 5141 N VARNA AVE 91423
- Application / Permit
- 22014-10000-02426
- Plan Check / Job No.
- B22LA09423
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2-STORY ADDITION TO SFD. 1 OF 2
- Permit Issued
- Issued on 12/7/2022
- Issuing Office
- Current Status
- CofO Issued on 1/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2022 | JOE VO |
| Corrections Issued | 6/20/2022 | JOE VO |
| Quality Review Completed | 6/23/2022 | GARO TELMI |
| Plan Check Approved | 11/29/2022 | JOE VO |
| Issued | 12/7/2022 | APPLICANT |
| CofO in Progress | 1/9/2024 | MISAEL ESPARZA |
| Permit Finaled | 1/16/2024 | RUBEN SALAS |
| CofO Issued | 1/16/2024 | RUBEN SALAS |
| Permit Finaled | 1/16/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 7/8/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 10/17/2022 | DEBORA LEITE |
| Permit | Cleared | 10/17/2022 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 10/17/2022 | COLIN LOREDO |
Contact Information
| Contractor | T & N Remodeling Inc; Lic. No.: 1063782-B | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 2/10/2023 | Corrections Issued | MISAEL ESPARZA |
| Pre-Inspection | 2/10/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 2/14/2023 | Partial Approval | MISAEL ESPARZA |
| Deputy Drilled-In Anchors | 2/22/2023 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Corrections Issued | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 2/27/2023 | Conditional Approval | MISAEL ESPARZA |
| Deputy Steel/Welding | 3/17/2023 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2023 | Partial Approval | MISAEL ESPARZA |
| Pre-Inspection | 3/30/2023 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Partial Approval | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2023 | Partial Approval | MISAEL ESPARZA |
| Footing/Foundation/Slab | 4/17/2023 | Approved | MISAEL ESPARZA |
| Deputy Wood Construction | 4/20/2023 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/23/2023 | Partial Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 5/23/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Rough | 5/23/2023 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 5/23/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Rough | 5/23/2023 | Approved | JOHN COLEMAN |
| Rough-Elec/Plmb/HVAC | 5/23/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Wood Frame | 5/23/2023 | Corrections Issued | JOHN COLEMAN |
| BUILDING-Rough-Frame | 6/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 6/8/2023 | Approved | JOHN COLEMAN |
| Green Building Rough | 6/8/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 6/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/14/2023 | Approved | JOHN COLEMAN |
| Shower Pan | 6/14/2023 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 6/20/2023 | Approved | JOHN COLEMAN |
| BUILDING-Rough-Frame | 7/5/2023 | Approved | MISAEL ESPARZA |
| Insulation | 7/26/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 8/4/2023 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/16/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 9/6/2023 | Approved | MISAEL ESPARZA |
| Sewer | 9/6/2023 | Corrections Issued | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/8/2023 | Approved | MISAEL ESPARZA |
| Sewer | 9/8/2023 | Approved | MISAEL ESPARZA |
| Gas Test | 9/15/2023 | Partial Approval | MISAEL ESPARZA |
| Special/Order Compliance | 9/15/2023 | Partial Inspection | MISAEL ESPARZA |
| Underground Mechanical | 9/15/2023 | Corrections Issued | MISAEL ESPARZA |
| Underground Mechanical | 9/19/2023 | Partial Approval | MISAEL ESPARZA |
| ELECTRICAL-Final | 11/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 11/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Gas Test | 11/30/2023 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 11/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| HVAC-Final | 11/30/2023 | No Access for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 11/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 11/30/2023 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 12/18/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/19/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/19/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 12/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 12/19/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 12/19/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | MISAEL ESPARZA |
| Service/Power Release | 12/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 12/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 12/21/2023 | No Access for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/26/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 12/26/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 12/26/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 12/26/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Final | 12/26/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/26/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 12/26/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 12/26/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 12/29/2023 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 12/29/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Final | 12/29/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 1/3/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/3/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 1/3/2024 | Approved | MISAEL ESPARZA |
| Service/Power Release | 1/3/2024 | Approved | MISAEL ESPARZA |
| Final | 1/8/2024 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 1/8/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 1/8/2024 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 1/8/2024 | Approved | MISAEL ESPARZA |