2406 N GLOVER PL 90031

Certificate Information: 2406 N GLOVER PL 90031

Application / Permit
22014-10000-02414
Plan Check / Job No.
B22LA09354
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO ADU WITH 2-STORY ADDITION AND ROOF DECK. ADU PER LAMC 12.22 A.33 (c) & (d)
Permit Issued
Issued on 11/3/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/27/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 6/2/2022 ADRIANA LOPEZ
Corrections Issued 6/10/2022 ADRIANA LOPEZ
Quality Review Completed 6/29/2022 KEN GILL
Building Plans Picked Up 7/1/2022 APPLICANT
Plan Check Approved 11/1/2022 ADRIANA LOPEZ
Issued 11/3/2022 APPLICANT
CofO in Progress 2/2/2024 THOMAS LOGRASSO
No Progress 2/8/2024 DEROLD HAUFF
Permit Finaled 2/27/2024 DEROLD HAUFF
CofO Issued 2/27/2024 DEROLD HAUFF
Permit Finaled 2/27/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/18/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 7/21/2022 CINDY QI
Sewer availability Cleared 7/21/2022 CINDY QI
ZI Cleared 8/10/2022 JASON CHAN
Construction near power lines Cleared 9/21/2022 RIDWAN HARDY
Construction within easement Cleared 9/21/2022 RIDWAN HARDY
Low Impact Development Cleared 10/3/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 10/4/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/1/2022 Corrections Issued THOMAS LOGRASSO
Underground Mechanical 12/1/2022 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 1/19/2023 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Rough 1/19/2023 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 1/23/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 1/23/2023 Not Ready for Inspection ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 3/3/2023 No Access for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 3/3/2023 No Access for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 3/6/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/22/2023 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 4/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 4/21/2023 Corrections Issued KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 4/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 4/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 4/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 4/26/2023 Partial Approval STUART CHAPMAN
Rough-Elec/Plmb/HVAC 5/1/2023 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/3/2023 Corrections Issued THOMAS LOGRASSO
Green Building Rough 5/3/2023 Approved THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 5/3/2023 Approved THOMAS LOGRASSO
Insulation 5/10/2023 Not Ready for Inspection THOMAS LOGRASSO
Drywall Nailing 6/2/2023 Conditional Approval ALIZAH MAYAGOITIA
Insulation 6/2/2023 Conditional Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/2/2023 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 6/9/2023 Partial Approval THOMAS LOGRASSO
Shower Pan 6/9/2023 Approved THOMAS LOGRASSO
HVAC-Rough 9/15/2023 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 10/3/2023 Corrections Issued ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 10/5/2023 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 11/20/2023 Approved THOMAS LOGRASSO
Drywall Nailing 11/20/2023 Approved THOMAS LOGRASSO
Final 11/20/2023 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 11/20/2023 Approved THOMAS LOGRASSO
Green Building Final 11/20/2023 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 11/20/2023 Approved THOMAS LOGRASSO
Final 12/5/2023 Not Ready for Inspection THOMAS LOGRASSO
Final 1/26/2024 Not Ready for Inspection THOMAS LOGRASSO
Final 2/1/2024 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 2/1/2024 Approved THOMAS LOGRASSO