2404 N GLOVER PL 90031
Certificate Information: 2404 N GLOVER PL 90031
- Application / Permit
- 22014-10000-02413
- Plan Check / Job No.
- B22LA09354
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1) PROPOSED GROUND FLOOR ADDITION TO (E) SFD.
- Permit Issued
- Issued on 11/3/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2022 | ADRIANA LOPEZ |
| Corrections Issued | 6/10/2022 | ADRIANA LOPEZ |
| Quality Review Completed | 6/29/2022 | KEN GILL |
| Building Plans Picked Up | 7/1/2022 | APPLICANT |
| Plan Check Approved | 11/1/2022 | ADRIANA LOPEZ |
| Issued | 11/3/2022 | APPLICANT |
| CofO in Progress | 12/7/2023 | THOMAS LOGRASSO |
| Permit Finaled | 12/30/2023 | DEROLD HAUFF |
| CofO Issued | 12/30/2023 | DEROLD HAUFF |
| Permit Finaled | 12/30/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2022 | CINDY QI |
| ZI | Cleared | 8/10/2022 | JASON CHAN |
| Low Impact Development | Cleared | 10/3/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/4/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Corrections Issued | THOMAS LOGRASSO |
| Underground Mechanical | 12/1/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/13/2022 | Approved | THOMAS LOGRASSO |
| Insulation | 12/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 1/31/2023 | Approved | THOMAS LOGRASSO |
| Sewer | 1/31/2023 | Approved | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 5/1/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 6/13/2023 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 6/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 6/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 6/15/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 6/20/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/20/2023 | Partial Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 6/20/2023 | Approved | JOSEPH MCGARRY |
| Wood Frame | 6/20/2023 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 6/23/2023 | Corrections Issued | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 6/23/2023 | Partial Approval | KATHRYN BUTTERWORTH |
| Shower Pan | 6/23/2023 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 6/28/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 6/28/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Insulation | 6/28/2023 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 7/5/2023 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 7/18/2023 | Conditional Approval | THOMAS LOGRASSO |
| HVAC-Rough | 9/15/2023 | Approved | THOMAS LOGRASSO |
| Deputy Wood Construction | 10/5/2023 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Wood Construction | 10/23/2023 | Conditional Approval | THOMAS LOGRASSO |
| Final | 11/16/2023 | Corrections Issued | THOMAS LOGRASSO |
| Green Building Final | 11/16/2023 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 11/16/2023 | SGSOV Approved | THOMAS LOGRASSO |
| Smoke Detectors | 11/16/2023 | Approved | THOMAS LOGRASSO |
| Final | 12/5/2023 | OK to Issue CofO | THOMAS LOGRASSO |