10620 W FES ST 91352

Certificate Information: 10620 W FES ST 91352

Application / Permit
22014-10000-02410
Plan Check / Job No.
B22LA09324
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERT DETACHED GARAGE INTO ADU PER LAMC 12.22 A.33 (c)(d)
Permit Issued
Issued on 7/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 1/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 5/19/2022 KHUONG TRUONG
Corrections Issued 5/23/2022 KHUONG TRUONG
Building Plans Picked Up 5/24/2022 APPLICANT
Plan Check Approved 7/11/2022 RICARDO RAMIREZ
Issued 7/18/2022 APPLICANT
CofO in Progress 11/27/2023 DAVID ANDERSON
Permit Finaled 1/3/2024 RUBEN SALAS
CofO Issued 1/3/2024 RUBEN SALAS
Permit Finaled 1/3/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/6/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 6/6/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 6/9/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 6/9/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 6/22/2022 PATRICK MAGALLANES

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/9/2022 Approved DAVID ANDERSON
Deputy Drilled-In Anchors 1/6/2023 Approved DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 1/6/2023 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Approved DAVID ANDERSON
PLUMBING-Rough 3/2/2023 Approved DAVID ANDERSON
Sewer 3/2/2023 Approved DAVID ANDERSON
Underground Mechanical 3/2/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 6/6/2023 Approved DAVID ANDERSON
Green Building Rough 6/6/2023 Approved DAVID ANDERSON
Interior/Exterior Lathing 6/6/2023 Approved DAVID ANDERSON
MERV13>=Rough 6/6/2023 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 6/6/2023 Approved DAVID ANDERSON
Insulation 8/3/2023 Approved WILLIAM WREN
Drywall Nailing 8/23/2023 Approved DAVID ANDERSON
Final 11/9/2023 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 11/9/2023 Approved DAVID ANDERSON
Green Building Final 11/9/2023 Approved DAVID ANDERSON
MERV13>=Final 11/9/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/9/2023 SGSOV Approved DAVID ANDERSON
Smoke Detectors 11/9/2023 Approved DAVID ANDERSON
Final 11/16/2023 OK to Issue CofO DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 11/16/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 11/16/2023 Approved DAVID ANDERSON