2676 S BARRY AVE 90064
Certificate Information: 2676 S BARRY AVE 90064
- Application / Permit
- 22014-10000-02388
- Plan Check / Job No.
- B22LA09192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- laundry room addition and remodel to (E) SFD
- Permit Issued
- Issued on 11/1/2022
- Issuing Office
- Current Status
- CofO Issued on 1/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2022 | SHANGQIN XIE |
| Corrections Issued | 6/1/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 7/27/2022 | SHANGQIN XIE |
| Plan Check Approved | 8/4/2022 | SHANGQIN XIE |
| Issued | 11/1/2022 | APPLICANT |
| CofO in Progress | 1/8/2024 | JESUS PINEDA |
| Permit Finaled | 1/8/2024 | DANIEL ORRANTE |
| CofO Issued | 1/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/22/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2022 | DINAH GARIN |
Contact Information
| Contractor | Ram Construction & Electrical; Lic. No.: 1064340-B | , |
| Contractor | The Contractor Gal; Lic. No.: 1064340-B | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 11/7/2022 | Corrections Issued | CLAYTON GRAHAM |
| Wood Frame | 11/7/2022 | Not Ready for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2022 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 11/8/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Partial Approval | JOHNNY MIRANDA |
| Deputy Wood Construction | 12/9/2022 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 12/12/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 12/12/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2022 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 12/12/2022 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/23/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/23/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/29/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 12/29/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 12/29/2022 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 12/29/2022 | Partial Approval | JOHNNY MIRANDA |
| Drywall Nailing | 1/9/2023 | No Access for Inspection | JOHNNY MIRANDA |
| Drywall Nailing | 1/12/2023 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 12/22/2023 | Approved | JESUS PINEDA |
| Final | 12/22/2023 | Corrections Issued | JESUS PINEDA |
| HVAC-Final | 12/22/2023 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Final | 12/22/2023 | Corrections Issued | JESUS PINEDA |
| Smoke Detectors | 12/22/2023 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 12/29/2023 | Approved | JESUS PINEDA |
| Final | 12/29/2023 | Not Ready for Inspection | JESUS PINEDA |
| HVAC-Final | 12/29/2023 | Approved | JESUS PINEDA |
| PLUMBING-Final | 12/29/2023 | Approved | JESUS PINEDA |
| Final | 1/2/2024 | Not Ready for Inspection | JESUS PINEDA |
| Final | 1/5/2024 | OK to Issue CofO | JESUS PINEDA |