2676 S BARRY AVE 90064

Certificate Information: 2676 S BARRY AVE 90064

Application / Permit
22014-10000-02388
Plan Check / Job No.
B22LA09192
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
laundry room addition and remodel to (E) SFD
Permit Issued
Issued on 11/1/2022
Issuing Office
Current Status
CofO Issued on 1/8/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2022 APPLICANT
Assigned to Plan Check Engineer 5/31/2022 SHANGQIN XIE
Corrections Issued 6/1/2022 SHANGQIN XIE
Applicant returned to address corrections 7/27/2022 SHANGQIN XIE
Plan Check Approved 8/4/2022 SHANGQIN XIE
Issued 11/1/2022 APPLICANT
CofO in Progress 1/8/2024 JESUS PINEDA
Permit Finaled 1/8/2024 DANIEL ORRANTE
CofO Issued 1/8/2024 DANIEL ORRANTE
Permit Finaled 1/8/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 7/22/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/26/2022 DINAH GARIN

Contact Information

Contractor Ram Construction & Electrical; Lic. No.: 1064340-B       ,
Contractor The Contractor Gal; Lic. No.: 1064340-B       ,

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 11/7/2022 Corrections Issued CLAYTON GRAHAM
Wood Frame 11/7/2022 Not Ready for Inspection CLAYTON GRAHAM
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval JOHNNY MIRANDA
Wood Frame 11/8/2022 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/9/2022 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 12/9/2022 Conditional Approval MICHAEL PELHAM
BUILDING-Rough-Frame 12/12/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 12/12/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 12/12/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 12/12/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 12/23/2022 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 12/23/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 12/29/2022 Approved JOHNNY MIRANDA
Green Building Rough 12/29/2022 Approved JOHNNY MIRANDA
Insulation 12/29/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 12/29/2022 Partial Approval JOHNNY MIRANDA
Drywall Nailing 1/9/2023 No Access for Inspection JOHNNY MIRANDA
Drywall Nailing 1/12/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Final 12/22/2023 Approved JESUS PINEDA
Final 12/22/2023 Corrections Issued JESUS PINEDA
HVAC-Final 12/22/2023 Corrections Issued JESUS PINEDA
PLUMBING-Final 12/22/2023 Corrections Issued JESUS PINEDA
Smoke Detectors 12/22/2023 Approved JESUS PINEDA
ELECTRICAL-Final 12/29/2023 Approved JESUS PINEDA
Final 12/29/2023 Not Ready for Inspection JESUS PINEDA
HVAC-Final 12/29/2023 Approved JESUS PINEDA
PLUMBING-Final 12/29/2023 Approved JESUS PINEDA
Final 1/2/2024 Not Ready for Inspection JESUS PINEDA
Final 1/5/2024 OK to Issue CofO JESUS PINEDA