2233 1/2 S BRONSON AVE 90018

Certificate Information: 2233 1/2 S BRONSON AVE 90018

Application / Permit
22014-10000-02373
Plan Check / Job No.
B22LA09112
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
GARAGE TO BE CONVERTED TO ADU WITH AN ADDITION PER DETACHED ADU ORDINANCE (2-STORY)
Permit Issued
Issued on 5/3/2023
Issuing Office
Current Status
Issued on 5/3/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/17/2022 APPLICANT
Assigned to Plan Check Engineer 5/27/2022 CARLOS MONTES
Corrections Issued 5/31/2022 CARLOS MONTES
Quality Review Completed 6/8/2022 MICHAEL PEREZ
Applicant returned to address corrections 2/8/2023 CARLOS MONTES
Plan Check Approved 3/9/2023 CARLOS MONTES
Issued 5/3/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/14/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 11/2/2022 JEANIE LAM
Sewer availability Cleared 11/2/2022 JEANIE LAM
Tenant Habitability Plan Cleared 11/3/2022 RICARDO BOHORQUEZ
Community Plan Implem. Overlay Cleared 11/15/2022 KYLE WINSTON
Low Impact Development Cleared 12/13/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 1/17/2023 JEANIE LAM
Construction near power lines Cleared 2/21/2023 RIDWAN HARDY

Contact Information

Contractor Sheene Paul Corporation; Lic. No.: 1015399-B       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2023 Corrections Issued CALEB MEISTER
METHANE-Barrier 5/16/2023 Not Ready for Inspection CALEB MEISTER
METHANE-Subgrade 5/16/2023 Not Ready for Inspection CALEB MEISTER
Pre-Inspection 5/26/2023 Not Ready for Inspection WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 6/2/2023 Partial Approval WILLIAM MICHALAK
Footing/Foundation/Slab 6/2/2023 Partial Approval WILLIAM MICHALAK
METHANE-Barrier 6/2/2023 Approved WILLIAM MICHALAK
METHANE-Subgrade 6/2/2023 Corrections Issued WILLIAM MICHALAK
Footing/Foundation/Slab 11/9/2023 Corrections Issued WILLIAM MICHALAK
METHANE-Rough 11/9/2023 Approved WILLIAM MICHALAK
METHANE-Subgrade 11/9/2023 Corrections Issued WILLIAM MICHALAK
Sewer 11/9/2023 Not Ready for Inspection WILLIAM MICHALAK
Excavation/Setback/Form/Re-Bar 11/15/2023 Not Ready for Inspection WILLIAM MICHALAK