5941 N TEXHOMA AVE 91316
Certificate Information: 5941 N TEXHOMA AVE 91316
- Application / Permit
- 22014-10000-02355
- Plan Check / Job No.
- B22LA09064
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL TO (E) SFR 806 SQ FT REMODEL TO (E) GARAGE 231 SQ FT ADDITION TO SFR 1363 SQ FT ADDITION TO GARAGE 84 SQ FT NFPA13-D FIRE SPRINKLERS REQUIRED
- Permit Issued
- Issued on 9/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2022 | ZAW HAN |
| Corrections Issued | 5/24/2022 | ZAW HAN |
| Building Plans Picked Up | 5/27/2022 | APPLICANT |
| Plan Check Approved | 9/22/2022 | ADAM HEGAZI |
| Issued | 9/22/2022 | APPLICANT |
| CofO in Progress | 7/14/2023 | JON MCHUGH |
| Permit Finaled | 7/18/2023 | DANIEL ORRANTE |
| CofO Issued | 7/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2022 | ROMAN GUTIERREZ |
| Sewer availability | Cleared | 6/14/2022 | ROMAN GUTIERREZ |
| ZI | Cleared | 6/29/2022 | SPENCER WEJROWSKI |
| Low Impact Development | Cleared | 9/14/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 9/15/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Elm Construction; Lic. No.: 1018660-B | 1489 S CANFIELD #203 LOS ANGELES, CA 90035 |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Footing/Foundation/Slab | 9/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Piling/Pier/Caisson | 9/28/2022 | Not Ready for Inspection | SEAN HAUPT |
| Pre-Inspection | 9/28/2022 | Approved | SEAN HAUPT |
| Deputy Drilled-In Anchors | 9/30/2022 | Conditional Approval | MORRIS JACKSON |
| Footing/Foundation/Slab | 10/11/2022 | Corrections Issued | DAVID SANDOVAL |
| Excavation/Setback/Form/Re-Bar | 10/17/2022 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 10/17/2022 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 11/14/2022 | Partial Approval | SEAN HAUPT |
| Underground Mechanical | 11/14/2022 | Not Ready for Inspection | SEAN HAUPT |
| Wood Frame | 11/14/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 11/17/2022 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 2/1/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 2/1/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 2/1/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 2/1/2023 | Corrections Issued | JON MCHUGH |
| Sewer | 2/1/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 2/1/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/1/2023 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 3/1/2023 | Approved | JON MCHUGH |
| Green Building Rough | 3/1/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 3/1/2023 | Approved | JON MCHUGH |
| Wood Frame | 3/1/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 3/8/2023 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 3/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 3/8/2023 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 3/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Interior/Exterior Lathing | 3/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 3/10/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/14/2023 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 3/14/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 3/14/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 3/14/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 3/14/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/20/2023 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 3/20/2023 | Partial Approval | JON MCHUGH |
| Wood Frame | 3/20/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 3/28/2023 | Corrections Issued | JON MCHUGH |
| Insulation | 3/28/2023 | Approved | JON MCHUGH |
| Wood Frame | 3/28/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/7/2023 | Corrections Issued | JON MCHUGH |
| Drywall Nailing | 4/7/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/7/2023 | Approved | JON MCHUGH |
| Green Building Final | 6/14/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | JON MCHUGH |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 7/13/2023 | Approved | JON MCHUGH |
| Final | 7/13/2023 | Corrections Issued | JON MCHUGH |
| HVAC-Final | 7/13/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 7/13/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/13/2023 | SGSOV Not Ready | JON MCHUGH |
| Service/Power Release | 7/13/2023 | Approved | JON MCHUGH |
| Smoke Detectors | 7/13/2023 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 7/13/2023 | Approved | JON MCHUGH |
| Final | 7/14/2023 | OK to Issue CofO | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 7/14/2023 | SGSOV Approved | JON MCHUGH |