10604 W BLYTHE AVE 90064
Certificate Information: 10604 W BLYTHE AVE 90064
- Application / Permit
- 22014-10000-02336
- Plan Check / Job No.
- B22LA08942
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ADDITION TO EXISTING ONE STORY SINGLE FAMILY RESIDENCE 167 SF, PROPOSED NEW COVERED PATIO 50 SF, NEW OPEN UNCOVERED WOOD DECK AT REAR OF BUILDING INTERIOR REMODEL
- Permit Issued
- Issued on 8/4/2022
- Issuing Office
- Current Status
- Issued on 8/4/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/12/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2022 | ZAW HAN |
| Corrections Issued | 5/24/2022 | ZAW HAN |
| Plan Check Approved | 7/1/2022 | KHUONG TRUONG |
| Issued | 8/4/2022 | APPLICANT |
| Building Plans Picked Up | 8/8/2022 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/24/2022 | MARITZA PRZEKOP |
| Grading Pre-Inspection | Cleared | 5/26/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 5/31/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2022 | DINAH GARIN |
| Specific Plan | Cleared | 6/7/2022 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 6/15/2022 | DINAH GARIN |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/17/2023 | Partial Approval | JOHNNY MIRANDA |
| METHANE-Barrier | 2/17/2023 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 2/17/2023 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/27/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Rough | 2/27/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 3/3/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/7/2023 | Partial Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 4/18/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 6/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 6/12/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 6/12/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 6/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/15/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 6/15/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 6/15/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/20/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 6/20/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/23/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 6/23/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 6/23/2023 | Partial Approval | JESUS PINEDA |
| Insulation | 6/30/2023 | Approved | CLAYTON GRAHAM |
| Shower Pan | 6/30/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Drywall Nailing | 7/6/2023 | Approved | CLAYTON GRAHAM |
| Shower Pan | 7/10/2023 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/12/2023 | Partial Approval | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 7/20/2023 | Approved | CLAYTON GRAHAM |
| Final | 8/6/2024 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 8/6/2024 | Approved | ASHLEY THOMPSON |
| Green Building Final | 8/6/2024 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 8/6/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 8/6/2024 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 8/6/2024 | Partial Inspection | REGINA MENDEZ |
| ELECTRICAL-Final | 10/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 10/16/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Final | 10/16/2024 | Approved | CARLOS MATAMOROS |
| HVAC-Final | 10/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| PLUMBING-Final | 10/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Smoke Detectors | 10/16/2024 | Approved | CARLOS MATAMOROS |