2110 W 94TH PL 90047

Certificate Information: 2110 W 94TH PL 90047

Application / Permit
22014-10000-02316
Plan Check / Job No.
B22LA08895
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 256.55 SF ADDITION TO REAR OF 1,079 SF HOUSE PER TYPE V
Permit Issued
Issued on 6/27/2022
Issuing Office
Metro
Current Status
CofO Issued on 6/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2022 APPLICANT
Assigned to Plan Check Engineer 5/13/2022 ZAW HAN
Corrections Issued 5/17/2022 ZAW HAN
Building Plans Picked Up 5/18/2022 APPLICANT
Plan Check Approved 6/9/2022 KHUONG TRUONG
Issued 6/27/2022 APPLICANT
CofO in Progress 6/5/2023 ENRIQUE MIRELES
CofO in Progress 6/5/2023 ENRIQUE MIRELES
Permit Finaled 6/8/2023 DEROLD HAUFF
CofO Issued 6/8/2023 DEROLD HAUFF
Permit Finaled 6/8/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/2/2022 JEANETTE VONG
Sewer availability Cleared 6/2/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 6/7/2022 JEANETTE VONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/3/2022 Approved ENRIQUE MIRELES
Footing/Foundation/Slab 9/13/2022 Approved ALIZAH MAYAGOITIA
METHANE-Barrier 9/13/2022 Approved ALIZAH MAYAGOITIA
METHANE-Subgrade 9/13/2022 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/28/2022 Not Ready for Inspection RYAN SALAZAR
ELECTRICAL-Rough 10/28/2022 Approved RYAN SALAZAR
Green Building Rough 10/28/2022 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 10/28/2022 Approved RYAN SALAZAR
METHANE-Rough 10/28/2022 Approved RYAN SALAZAR
PLUMBING-Rough 10/28/2022 Approved RYAN SALAZAR
Rough-Elec/Plmb/HVAC 10/28/2022 Approved RYAN SALAZAR
Insulation 11/4/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/4/2022 Approved ENRIQUE MIRELES
Drywall Nailing 11/8/2022 Approved ENRIQUE MIRELES
Green Building Rough 11/8/2022 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 11/8/2022 Corrections Issued ENRIQUE MIRELES
Interior/Exterior Lathing 11/16/2022 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/18/2023 Approved ENRIQUE MIRELES
Final 4/18/2023 Corrections Issued ENRIQUE MIRELES
Green Building Final 4/18/2023 Approved ENRIQUE MIRELES
HVAC-Final 4/18/2023 Approved ENRIQUE MIRELES
PLUMBING-Final 4/18/2023 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 4/18/2023 SGSOV Approved ENRIQUE MIRELES
Service/Power Release 4/18/2023 Approved ENRIQUE MIRELES
Smoke Detectors 4/18/2023 Approved ENRIQUE MIRELES
Final 6/1/2023 OK to Issue CofO ENRIQUE MIRELES
HVAC-Final 6/1/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 6/1/2023 Approved ENRIQUE MIRELES