5452 W 77TH ST 90045
Certificate Information: 5452 W 77TH ST 90045
- Application / Permit
- 22014-10000-02283
- Plan Check / Job No.
- B22LA08809
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan ADDITION TO (E) REC ROOM TO BE CONVERTED IN TO ADU
- Permit Issued
- Issued on 7/29/2022
- Issuing Office
- Current Status
- CofO Issued on 5/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2022 | RAHEL BEYENE |
| Corrections Issued | 5/17/2022 | FERNANDO FLORES |
| Applicant returned to address corrections | 5/26/2022 | FERNANDO FLORES |
| Plan Check Approved | 7/24/2022 | RAHEL BEYENE |
| Issued | 7/29/2022 | APPLICANT |
| CofO in Progress | 5/4/2023 | BOBBY KEY |
| Permit Finaled | 5/6/2023 | DANIEL ORRANTE |
| CofO Issued | 5/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2022 | CATHERINE ADROVER |
| Specific Plan | Cleared | 5/24/2022 | WESTON PRINGLE |
| Roof/Waste drainage to street | Cleared | 5/25/2022 | CATHERINE ADROVER |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | CATHERINE ADROVER |
| Sewer availability | Cleared | 5/26/2022 | CATHERINE ADROVER |
| Grading Pre-Inspection | Cleared | 6/13/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 7/20/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Superior Home Remodeling Inc; Lic. No.: 1048870-B | 14011 VENTURA BLVD #207E SHERMAN OAKS, CA 91423 |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/29/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/29/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 12/29/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2022 | Partial Approval | BOBBY KEY |
| MERV13>=Rough | 12/29/2022 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 12/29/2022 | Not Ready for Inspection | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2023 | Conditional Approval | BOBBY KEY |
| Gas Test | 1/19/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 1/19/2023 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/19/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 1/24/2023 | Conditional Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/24/2023 | Approved | BOBBY KEY |
| Green Building Rough | 1/24/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 1/24/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 1/24/2023 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 2/1/2023 | Not Ready for Inspection | BOBBY KEY |
| Insulation | 2/1/2023 | Not Ready for Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 2/1/2023 | Not Ready for Inspection | BOBBY KEY |
| MERV13>=Rough | 2/1/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 2/1/2023 | Corrections Issued | BOBBY KEY |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | BOBBY KEY |
| Insulation | 2/8/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/8/2023 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 2/21/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 2/21/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/21/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 4/7/2023 | Corrections Issued | HERBERT GIRON |
| Final | 4/7/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 4/7/2023 | Corrections Issued | HERBERT GIRON |
| MERV13>=Final | 4/7/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 4/7/2023 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/7/2023 | SGSOV Not Ready | HERBERT GIRON |
| Smoke Detectors | 4/7/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Not Ready | BOBBY KEY |
| ELECTRICAL-Final | 5/1/2023 | Approved | BOBBY KEY |
| Final | 5/1/2023 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Final | 5/1/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 5/1/2023 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 5/1/2023 | SGSOV Approved | BOBBY KEY |
| Final | 5/4/2023 | OK to Issue CofO | BOBBY KEY |
| PLUMBING-Final | 5/4/2023 | Approved | BOBBY KEY |
| Service/Power Release | 5/4/2023 | Approved | BOBBY KEY |