13439-13441 N NORRIS AVE 91342
Certificate Information: 13439-13441 N NORRIS AVE 91342
- Application / Permit
- 22014-10000-02282
- Plan Check / Job No.
- B22LA08808
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT AND EXPAND (E) ATTACHED GARAGE INTO A.D.U. PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 7/15/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2022 | APPLICANT |
| Corrections Issued | 5/12/2022 | LAWRENCE QUIRANTE |
| Assigned to Plan Check Engineer | 5/13/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 5/18/2022 | APPLICANT |
| Corrections Issued | 7/8/2022 | ADAM HEGAZI |
| Applicant returned to address corrections | 7/8/2022 | ADAM HEGAZI |
| Plan Check Approved | 7/12/2022 | ADAM HEGAZI |
| Issued | 7/15/2022 | APPLICANT |
| CofO in Progress | 12/15/2022 | ARAM AVEDISIAN |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/18/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 5/18/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 5/19/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 7/12/2022 | ALEXANDER HELFER |
Contact Information
| Contractor | Ramirez Construction Co; Lic. No.: 1023300-B | 2636 PINE PL SOUTH GATE, CA 90280 |
| Engineer | Wu,, Harold Ping-Hung; Lic. No.: C35693 | 1168 SAN GABRIEL BLVD NO N ROSEMEAD, CA 91770 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/18/2022 | No Result Entered | KENNETH KUROWSKI |
| Excavation/Setback/Form/Re-Bar | 8/24/2022 | Approved | ARAM AVEDISIAN |
| Sewer | 8/24/2022 | Approved | ARAM AVEDISIAN |
| Underground Mechanical | 8/24/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 9/12/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 9/12/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 9/12/2022 | Conditional Approval | ARAM AVEDISIAN |
| HVAC-Rough | 9/12/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/12/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 9/16/2022 | Conditional Approval | CALEB MEISTER |
| Interior/Exterior Lathing | 9/16/2022 | Approved | CALEB MEISTER |
| Shower Pan | 9/16/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 9/20/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 9/27/2022 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/5/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| Final | 12/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/12/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 12/12/2022 | Approved | JENNIFER RABUCHIN |
| Final | 12/15/2022 | OK to Issue CofO | ARAM AVEDISIAN |