1467 W 2ND ST 90732

Certificate Information: 1467 W 2ND ST 90732

Application / Permit
22014-10000-02275
Plan Check / Job No.
B22LA08793
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition at rear of SFD consisting of new Master Bedroom, bath, and closet.
Permit Issued
Issued on 10/26/2022
Issuing Office
Current Status
CofO Issued on 11/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2022 APPLICANT
Assigned to Plan Check Engineer 5/11/2022 JOE VO
Corrections Issued 5/12/2022 JOE VO
Plan Check Approved 7/24/2022 JOE VO
Issued 10/26/2022 APPLICANT
CofO in Progress 11/7/2024 JOSEPH MCGARRY
Permit Finaled 11/7/2024 ANSON MAGLASANG
CofO Issued 11/7/2024 ANSON MAGLASANG

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/14/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 6/21/2022 HUGO LOPEZ
Sewer availability Cleared 6/22/2022 HUGO LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Jordan,, Dale; Lic. No.: C63246 51 CALLE CABRILLO      FOOTHILL RANCH, CA 92610

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2023 Approved JOHN KLARIN
Deputy Drilled-In Anchors 7/27/2023 Conditional Approval ANSON MAGLASANG
Deputy Drilled-In Anchors 8/9/2023 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 8/11/2023 Partial Approval ANSON MAGLASANG
Gas Test 8/29/2023 Approved JAMES CHAVEZ
Insulation 8/29/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 8/29/2023 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 10/24/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 10/24/2023 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/24/2023 Partial Approval EUGENE CASSIDY
Green Building Rough 10/24/2023 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 10/24/2023 Approved EUGENE CASSIDY
Insulation 11/17/2023 Approved ANSON MAGLASANG
Drywall Nailing 11/27/2023 Not Ready for Inspection JAMES CHAVEZ
Interior/Exterior Lathing 11/27/2023 Not Ready for Inspection JAMES CHAVEZ
Drywall Nailing 11/30/2023 Approved ANSON MAGLASANG
Interior/Exterior Lathing 12/19/2023 Corrections Issued JAMES CHAVEZ
Shower Pan 12/22/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 1/2/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/10/2024 Approved EUGENE CASSIDY
Final 6/10/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 6/10/2024 Approved EUGENE CASSIDY
Green Building Final 6/10/2024 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 6/10/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/10/2024 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 6/10/2024 Approved EUGENE CASSIDY
Final 10/9/2024 Not Ready for Inspection JOSEPH MCGARRY
Green Building Final 10/9/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/9/2024 SGSOV Not Ready JOSEPH MCGARRY
Final 11/6/2024 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Approved JOSEPH MCGARRY