338 N VISTA ST 90036
Certificate Information: 338 N VISTA ST 90036
- Application / Permit
- 22014-10000-02262
- Plan Check / Job No.
- B22LA08755
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan ADDITION AND REMODEL TO EXISTING SFD
- Permit Issued
- Issued on 12/31/2022
- Issuing Office
- Current Status
- CofO Corrected on 3/19/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/9/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 6/21/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 7/1/2022 | FARUK SEZER |
| Plan Check Approved | 10/14/2022 | CRYSTEL MAALOUF |
| Issued | 12/31/2022 | APPLICANT |
| CofO in Progress | 11/20/2025 | JOSH MEISTER |
| Permit Finaled-Status Void | 11/22/2025 | DEROLD HAUFF |
| CofO Issued-Status Void | 11/22/2025 | DEROLD HAUFF |
| Re-Activate Permit | 3/19/2026 | DEROLD HAUFF |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
| CofO Corrected | 3/19/2026 | DEROLD HAUFF |
| Permit Finaled | 3/19/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/16/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 10/7/2022 | ABEL CASILLAS |
| Sewer availability | Cleared | 10/7/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Maipo Build; Lic. No.: 1077541-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/1/2023 | Conditional Approval | MICHAEL LEWIS |
| Excavation/Setback/Form/Re-Bar | 2/6/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 2/6/2023 | Partial Approval | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 2/21/2023 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2023 | Partial Approval | MICHAEL LEWIS |
| Deputy Drilled-In Anchors | 3/28/2023 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/11/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/11/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/15/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 9/15/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 9/15/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 11/15/2023 | Partial Approval | LILIANA PORTILLO |
| METHANE-Rough | 11/15/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 11/16/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 11/16/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 11/27/2023 | Approved | LILIANA PORTILLO |
| Insulation | 11/27/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 12/11/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/11/2023 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 5/20/2024 | Approved | AMIR NAZARIAN |
| Shower Pan | 5/20/2024 | Partial Approval | AMIR NAZARIAN |
| Interior/Exterior Lathing | 6/10/2024 | Approved | AMY COLIN |
| Shower Pan | 6/10/2024 | Approved | AMY COLIN |
| Sewer | 6/30/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 6/30/2025 | Conditional Approval | JOSE MACIAS |
| Sewer | 9/12/2025 | Approved | JOSE MACIAS |
| Underground Mechanical | 9/12/2025 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 10/17/2025 | Approved | JOSH MEISTER |
| Gas Test | 10/17/2025 | Approved | JOSH MEISTER |
| HVAC-Final | 10/17/2025 | Approved | JOSH MEISTER |
| PLUMBING-Final | 10/17/2025 | Approved | JOSH MEISTER |
| Final | 10/30/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 10/30/2025 | Approved | ENRIQUE MIRELES |
| METHANE-Barrier | 10/30/2025 | Approved | ENRIQUE MIRELES |
| METHANE-Subgrade | 10/30/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/30/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/30/2025 | Approved | ENRIQUE MIRELES |
| Final | 11/5/2025 | OK to Issue CofO | JOSH MEISTER |