4207 3/4 W EXPOSITION BLVD 90016

Certificate Information: 4207 3/4 W EXPOSITION BLVD 90016

Application / Permit
22014-10000-02260
Plan Check / Job No.
B22LA08753
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Addition to existing garage to convert to ADU per Ordinance.
Permit Issued
Issued on 11/15/2022
Issuing Office
Current Status
Issued on 11/15/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/23/2022 APPLICANT
Assigned to Plan Check Engineer 5/24/2022 RICARDO RAMIREZ
Corrections Issued 5/25/2022 RICARDO RAMIREZ
Applicant returned to address corrections 10/19/2022 LUKE GONZALES
Plan Check Approved 10/23/2022 RICARDO RAMIREZ
Issued 11/15/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/7/2022 CINDY QI
Roof/Waste drainage to street Cleared 6/7/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 6/16/2022 CINDY QI
Metro Rail approval Cleared 6/16/2022 RICARDO RAMIREZ
Sewer availability Cleared 6/16/2022 CINDY QI
Tenant Habitability Plan Cleared 6/27/2022 RICARDO BOHORQUEZ
Construction near power lines Cleared 8/20/2022 RIDWAN HARDY

Contact Information

Architect Best,, Richard Allen; Lic. No.: C17334 1275 BEVERLY ESTATES DR.      BEVERLY HILLS, CA 90210
Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/5/2024 Conditional Approval MARTIN TAVITIAN
Footing/Foundation/Slab 12/5/2024 Partial Approval MARTIN TAVITIAN
METHANE-Barrier 12/5/2024 Partial Approval MARTIN TAVITIAN
METHANE-Subgrade 12/5/2024 Conditional Approval MARTIN TAVITIAN
Floor/Roof Diaphrgm/Shear Wall 1/29/2025 Not Ready for Inspection RAFAEL CORTES
METHANE-Rough 1/29/2025 Not Ready for Inspection RAFAEL CORTES
Wood Frame 1/29/2025 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Corrections Issued JUSTIN HAWLEY
Footing/Foundation/Slab 1/31/2025 Approved JUSTIN HAWLEY
Pre-Inspection 1/31/2025 Corrections Issued JUSTIN HAWLEY
Floor/Roof Diaphrgm/Shear Wall 2/25/2025 Approved LUIS CASTRO
METHANE-Rough 2/25/2025 Approved LUIS CASTRO
Interior/Exterior Lathing 3/4/2025 Corrections Issued ENRIQUE MIRELES
Wood Frame 3/4/2025 Not Ready for Inspection ENRIQUE MIRELES
Interior/Exterior Lathing 3/7/2025 Approved ARTHUR NEGRETE
Wood Frame 3/7/2025 Approved ARTHUR NEGRETE
Insulation 3/11/2025 Approved JEFFREY MEAD
Drywall Nailing 3/19/2025 Approved ALEX COLIN
Interior/Exterior Lathing 3/19/2025 Approved ALEX COLIN
Pre-Inspection 3/26/2025 Not Ready for Inspection JOSE MACIAS