3632 N LAUREL CANYON BLVD 91604

Certificate Information: 3632 N LAUREL CANYON BLVD 91604

Application / Permit
22014-10000-02259
Plan Check / Job No.
B22LA08752
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERTING (E) DETACHED CAR GARAGE (360 SF) + NEW ADDITION (446 SF) TO THE NEW DETACHED ADU (TOTAL IS 806 SF)
Permit Issued
Issued on 12/26/2022
Issuing Office
Current Status
Issued on 12/26/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/10/2022 APPLICANT
Assigned to Plan Check Engineer 5/15/2022 RICARDO RAMIREZ
Corrections Issued 5/17/2022 RICARDO RAMIREZ
Plan Check Approved 12/23/2022 RAHEL BEYENE
Issued 12/26/2022 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/25/2022 KIRK LINKLATER
Hydrant and Access approval Cleared 10/26/2022 LAVEON RIDER
Address approval Cleared 10/27/2022 LEE GUILBEAUX
BHO/Hillside ordinance Cleared 10/27/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/27/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/27/2022 LEE GUILBEAUX
Sewer availability Cleared 10/27/2022 LEE GUILBEAUX
Street Frontage Cleared 11/18/2022 AMAAN MALIK
GPI Written Notices Cleared 12/21/2022 RICARDO RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Tan,, Charles; Lic. No.: NA4758       ,

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/18/2023 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 12/18/2023 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 12/19/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 12/19/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/5/2024 Approved CHRISTOPHE COCHRAN
Underground Mechanical 1/5/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 2/13/2024 Not Ready for Inspection JOHN COLEMAN
Verify Sprinkler Sign Off 2/13/2024 Not Ready for Inspection JOHN COLEMAN
Wood Frame 2/13/2024 Corrections Issued JOHN COLEMAN
PLUMBING-Rough 3/1/2024 Approved CHRISTOPHE COCHRAN
Sewer 3/1/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 4/9/2024 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 5/21/2024 Corrections Issued CHRISTOPHE COCHRAN
Insulation 5/21/2024 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 3/27/2025 Approved CHRISTOPHE COCHRAN
HVAC-Rough 3/27/2025 Approved CHRISTOPHE COCHRAN
Insulation 3/27/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 5/19/2025 Corrections Issued CHRISTOPHE COCHRAN
Insulation 5/19/2025 Corrections Issued CHRISTOPHE COCHRAN
Interior/Exterior Lathing 5/19/2025 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 5/19/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/24/2026 Corrections Issued CHRISTOPHE COCHRAN
Insulation 4/24/2026 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 4/24/2026 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 4/24/2026 Not Ready for Inspection CHRISTOPHE COCHRAN