309 W 118TH PL 90061

Certificate Information: 309 W 118TH PL 90061

Application / Permit
22014-10000-02252
Plan Check / Job No.
B22LA08738
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to existing garage to convert into ADU per LAMC 12.22 A33 (c) &(d).
Permit Issued
Issued on 7/15/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/10/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2022 APPLICANT
Assigned to Plan Check Engineer 5/11/2022 ZAW HAN
Corrections Issued 5/13/2022 ZAW HAN
Building Plans Picked Up 5/17/2022 APPLICANT
Issued 7/15/2022 APPLICANT
CofO in Progress 3/29/2023 JOHN KLARIN
Permit Finaled 5/10/2023 DANIEL ORRANTE
CofO Issued 5/10/2023 DANIEL ORRANTE
Permit Finaled 5/10/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 7/5/2022 JASON SHEETS
Address approval Cleared 7/14/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 7/14/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 7/15/2022 AMAAN MALIK
Sewer availability Cleared 7/15/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/19/2022 Approved JOHN KLARIN
METHANE-Barrier 8/19/2022 Approved JOHN KLARIN
METHANE-Subgrade 8/19/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 12/20/2022 Not Ready for Inspection JOHN KLARIN
Green Building Rough 12/20/2022 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 12/20/2022 Not Ready for Inspection JOHN KLARIN
METHANE-Rough 12/20/2022 Not Ready for Inspection JOHN KLARIN
PLUMBING-Rough 12/20/2022 Approved JOHN KLARIN
BUILDING-Rough-Frame 1/3/2023 Approved JOHN KLARIN
Green Building Rough 1/3/2023 Approved JOHN KLARIN
MERV13>=Rough 1/3/2023 Approved JOHN KLARIN
METHANE-Rough 1/3/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 1/5/2023 Approved JOHN KLARIN
HVAC-Rough 1/5/2023 Approved JOHN KLARIN
PLUMBING-Rough 1/5/2023 Corrections Issued JOHN KLARIN
Insulation 1/13/2023 Approved JOHN KLARIN
Drywall Nailing 1/19/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 1/19/2023 Approved JAMES CHAVEZ
ELECTRICAL-Final 3/13/2023 Corrections Issued JAMES CHAVEZ
Final 3/13/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 3/13/2023 Corrections Issued JAMES CHAVEZ
HVAC-Final 3/13/2023 Approved JAMES CHAVEZ
MERV13>=Final 3/13/2023 Approved JAMES CHAVEZ
PLUMBING-Final 3/13/2023 Corrections Issued JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/13/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 3/13/2023 Approved JAMES CHAVEZ
HVAC-Final 3/22/2023 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/22/2023 SGSOV Not Ready JAMES CHAVEZ
ELECTRICAL-Final 3/28/2023 Approved JOHN KLARIN
Final 3/28/2023 OK to Issue CofO JOHN KLARIN
Green Building Final 3/28/2023 Approved JOHN KLARIN
HVAC-Final 3/28/2023 Approved JOHN KLARIN
PLUMBING-Final 3/28/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/28/2023 SGSOV Approved JOHN KLARIN