7100 1/2 S FIGUEROA ST 90003

Certificate Information: 7100 1/2 S FIGUEROA ST 90003

Application / Permit
22014-10000-02209
Plan Check / Job No.
B22LA08518
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION/REMODEL TO THE EXISTING GARAGE AND CONVERT TO ADU
Permit Issued
Issued on 10/12/2022
Issuing Office
Current Status
CofO Issued on 12/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2022 APPLICANT
Assigned to Plan Check Engineer 5/13/2022 JOE VO
Corrections Issued 5/15/2022 JOE VO
Plan Check Approved 10/11/2022 JOE VO
Issued 10/12/2022 APPLICANT
CofO in Progress 12/18/2024 MICHAEL LEWIS
Permit Finaled 12/18/2024 DEROLD HAUFF
CofO Issued 12/18/2024 DEROLD HAUFF
Permit Finaled 12/18/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/2/2022 JEANETTE VONG
Community Plan Implem. Overlay Cleared 8/17/2022 RAFAEL FONTES
Eng Process Fee Ord 176,300 Cleared 8/23/2022 JEANETTE VONG
Sewer availability Cleared 8/23/2022 JEANETTE VONG
Low Impact Development Cleared 8/25/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 8/30/2022 JEANETTE VONG
Redevelopment Project Area Cleared 10/6/2022 DAVID URITA

Contact Information

Contractor Swami International Inc; Lic. No.: 833804-B       ,
Engineer Kazemi,, Milad; Lic. No.: NA92143       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/8/2023 Partial Inspection STUART CHAPMAN
Footing/Foundation/Slab 6/22/2023 Approved STUART CHAPMAN
PLUMBING-Rough 6/22/2023 Partial Approval STUART CHAPMAN
Sewer 6/22/2023 Partial Approval STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 7/12/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/27/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/30/2024 Not Ready for Inspection RONNIE MINDANAO
ELECTRICAL-Rough 1/30/2024 Approved RONNIE MINDANAO
Green Building Rough 1/30/2024 Approved RONNIE MINDANAO
MERV13>=Rough 1/30/2024 Not Ready for Inspection RONNIE MINDANAO
Shower Pan 1/30/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 3/6/2024 Corrections Issued JOSEPH MCGARRY
MERV13>=Rough 3/6/2024 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 3/6/2024 Approved JOSEPH MCGARRY
Rough-Elec/Plmb/HVAC 3/6/2024 Corrections Issued JOSEPH MCGARRY
Shower Pan 3/6/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 4/11/2024 Corrections Issued JOSE MACIAS
HVAC-Rough 4/11/2024 Approved JOSE MACIAS
MERV13>=Rough 4/11/2024 Approved JOSE MACIAS
Rough-Elec/Plmb/HVAC 4/11/2024 Not Ready for Inspection JOSE MACIAS
Insulation 7/12/2024 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 7/12/2024 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 8/2/2024 Corrections Issued DAVID FEILER
ELECTRICAL-Rough 8/2/2024 Partial Approval DAVID FEILER
Interior/Exterior Lathing 8/2/2024 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 8/20/2024 Approved CRAIG DAVIS
Insulation 8/20/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 8/20/2024 Approved CRAIG DAVIS
Drywall Nailing 8/22/2024 Approved ALEX COLIN
ELECTRICAL-Final 10/2/2024 Approved JOHN QUINTANILLA
Final 11/14/2024 Corrections Issued CRAIG DAVIS
Green Building Final 11/14/2024 Approved CRAIG DAVIS
MERV13>=Final 11/14/2024 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Not Required CRAIG DAVIS
Smoke Detectors 11/14/2024 Approved CRAIG DAVIS
Final 12/17/2024 OK to Issue CofO MICHAEL LEWIS
MERV13>=Final 12/17/2024 Approved MICHAEL LEWIS