8556 1/2 W HORNER ST 90035

Certificate Information: 8556 1/2 W HORNER ST 90035

Application / Permit
22014-10000-02208
Plan Check / Job No.
B22LA08517
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: New ADU over existing parking garage.
Permit Issued
Issued on 10/31/2023
Issuing Office
Current Status
CofO Issued on 11/25/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2022 APPLICANT
Assigned to Plan Check Engineer 6/9/2022 ARSALAN SHABESTARI
Corrections Issued 7/6/2022 ARSALAN SHABESTARI
Quality Review Completed 7/7/2022 FARUK SEZER
Applicant returned to address corrections 10/31/2022 ARSALAN SHABESTARI
Plan Check Approved 12/25/2022 ARSALAN SHABESTARI
Issued 10/31/2023 APPLICANT
CofO in Progress 11/19/2024 MEL KHACHATOURIAN
Permit Finaled 11/25/2024 RICHARD STEINBACH
CofO Issued 11/25/2024 RICHARD STEINBACH
Permit Finaled 11/25/2024 RICHARD STEINBACH

Permit Application Clearance Information

"Q" conditions Cleared 7/19/2022 DANIEL CORONADO
Address approval Cleared 7/21/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 7/21/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 7/22/2022 CELINA MORENO
Sewer availability Cleared 7/22/2022 CELINA MORENO
Construction near power lines Cleared 10/7/2022 RIDWAN HARDY
Construction within easement Cleared 10/7/2022 RIDWAN HARDY
Low Impact Development Cleared 2/13/2023 CHRIS VONG

Contact Information

Contractor Dexterous Creative Contractors & Design Inc; Lic. No.: 1075451-B       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/16/2024 Partial Approval MEL KHACHATOURIAN
METHANE-Barrier 2/16/2024 Approved MEL KHACHATOURIAN
METHANE-Subgrade 2/16/2024 Approved MEL KHACHATOURIAN
Footing/Foundation/Slab 3/1/2024 Approved CARLOS MATAMOROS
Deputy Drilled-In Anchors 3/29/2024 No Access for Inspection MEL KHACHATOURIAN
Deputy Wood Construction 4/16/2024 No Access for Inspection MEL KHACHATOURIAN
Deputy Wood Construction 4/23/2024 No Access for Inspection MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 4/26/2024 Corrections Issued MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Partial Approval MEL KHACHATOURIAN
Underground Mechanical 5/8/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Rough 5/20/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 6/14/2024 No Access for Inspection MEL KHACHATOURIAN
HVAC-Rough 6/18/2024 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 6/18/2024 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 6/21/2024 Approved MEL KHACHATOURIAN
METHANE-Rough 6/21/2024 Approved MEL KHACHATOURIAN
Insulation 6/25/2024 Approved MEL KHACHATOURIAN
Drywall Nailing 7/8/2024 Approved SEAN HAUPT
Interior/Exterior Lathing 7/15/2024 Partial Approval MEL KHACHATOURIAN
Sewer 8/2/2024 Corrections Issued MEL KHACHATOURIAN
Sewer 8/6/2024 Partial Approval MEL KHACHATOURIAN
Sewer 8/9/2024 Approved MEL KHACHATOURIAN
Shower Pan 8/9/2024 Approved MEL KHACHATOURIAN
Interior/Exterior Lathing 8/16/2024 Approved MEL KHACHATOURIAN
Gas Test 8/26/2024 Approved MEL KHACHATOURIAN
Underground Mechanical 8/30/2024 Partial Approval MEL KHACHATOURIAN
ELECTRICAL-Final 10/2/2024 Not Ready for Inspection MEL KHACHATOURIAN
ELECTRICAL-Final 10/22/2024 Approved MEL KHACHATOURIAN
HVAC-Final 10/22/2024 Not Ready for Inspection MEL KHACHATOURIAN
Smoke Detectors 10/22/2024 Approved MEL KHACHATOURIAN
PLUMBING-Rough 10/24/2024 No Access for Inspection MEL KHACHATOURIAN
HVAC-Final 11/1/2024 Corrections Issued BOBBY KEY
PLUMBING-Final 11/1/2024 Corrections Issued BOBBY KEY
Final 11/14/2024 Corrections Issued MEL KHACHATOURIAN
HVAC-Final 11/14/2024 Approved MEL KHACHATOURIAN
PLUMBING-Final 11/14/2024 Approved MEL KHACHATOURIAN
SGSOV-Seismic Gas S/O Valve 11/14/2024 SGSOV Approved MEL KHACHATOURIAN
Service/Power Release 11/19/2024 Approved MEL KHACHATOURIAN
Final 11/20/2024 OK to Issue CofO MEL KHACHATOURIAN